Pass Your Microsoft 70-178 Exam Easy!

Get 100% Real Exam Questions, Accurate & Verified Answers By IT Experts

Fast Updates & Instant Download!

Certification Exam: 70-178 (Microsoft Project 2010, Managing Projects)

Download Free 70-178 Exam Questions

Exam 70-178 - Microsoft Project 2010, Managing Projects
Size: 537.38 KB
Posted Date: Friday, June 21, 2013
# of downloads: 1099
Free Download:
  Download Free 70-178 Exam Questions
Exam
70-178 - Microsoft Project 2010, Managing Projects
Size
537.38 KB
Posted Date
Friday, June 21, 2013
# of downloads
1099
Comments
* The most recent comment are at the top
  • Giftedhandz
  • South Africa
  • Sep 26, 2015

please does anyone know if this dumps are still valid?

  • Sep 26, 2015
  • zofokawe
  • Germany
  • Jun 10, 2015

Valid in Belgium, scored 820/1000.

  • Jun 10, 2015
  • Ruben
  • Germany
  • May 22, 2015

Still valid in germany

  • May 22, 2015
  • Soni Thomas
  • United States
  • Mar 12, 2015

Does anyone have the latest dump available.I see no activity after 2013.It will be of great help...Thanks in Advance

  • Mar 12, 2015
  • Sejal Ray
  • India
  • Mar 21, 2014

Can anyone provide correct answers of the questions that are answered wrongly? It will help a lot

  • Mar 21, 2014
  • Pete
  • United States
  • Mar 16, 2014

Right on, still current with the test I took in March 2014

  • Mar 16, 2014
  • Somoy
  • Bangladesh
  • Mar 06, 2014

passed exam on Mar 6, 2014.
Thanks Ethan.
This dump is valid.
However, answers need corrections.

  • Mar 06, 2014
  • Protoshadow
  • South Africa
  • Feb 24, 2014

Going to write the exam in a week or two. Is this exam still valid or can anyone tell me where I can find an up to date version?

  • Feb 24, 2014
  • forster
  • Belgium
  • Feb 22, 2014

I passed 10th with 730/1000

  • Feb 22, 2014
  • anand
  • India
  • Feb 01, 2014

Is this still valid,will give exam next week,Please confirm if any one given exam recently, thx

  • Feb 01, 2014
  • Gabriel
  • Brazil
  • Nov 25, 2013

About the question "You need to cancel the Develop prototype based on functional specifications task..."

I research and found this information: http://office.microsoft.com/en-us/project-help/inactivate-a-task-HA010370341.aspx

in my opnion the correct answer is: inactive the task and make the task 100 percent complete.

  • Nov 25, 2013
  • tushar
  • India
  • Nov 02, 2013

Dump 100% valid. but few answers need validation, however sufficient to pass with 850+ marks.

  • Nov 02, 2013
  • djneo
  • United States
  • Oct 31, 2013

Valid dump!!. Questions 100% valid.(10-31-2013). Answers need validation.

  • Oct 31, 2013
  • EMMANUEL
  • United States
  • Oct 21, 2013

Good study material. I passed the test

  • Oct 21, 2013
  • Dutch
  • Netherlands
  • Oct 17, 2013

Valid yesterday in the Netherlands. All questions were from this dump, but some of the answers must be wrong. it's enough to get an 800-something passing grade though.

  • Oct 17, 2013
  • Nagy
  • Egypt
  • Sep 26, 2013

Passed today (26-09-2013). Questions 100% valid. But answers need validation!!

  • Sep 26, 2013
  • legolas
  • Azerbaijan
  • Sep 25, 2013

Valid, passed today 820, thanks to Ethan

  • Sep 25, 2013
  • skotti
  • Morocco
  • Sep 02, 2013

Dump 100% valid got 913

  • Sep 02, 2013
  • Cid from Brazil
  • Brazil
  • Jul 26, 2013

For the question:
You create a custom Timeline view of summary tasks and key milestones. You need to send an image of only the custom Timeline view by e-mail. Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)

The correct answer is:
"On the Format tab, select Copy Timeline, and then click For email." and "Copy and paste the Timeline view into the body of the e-mail."

instead of:
"On the File menu, select Save & Send, and then click Create a PDF/XPS Document." and "On the File menu, select Save & Send, and then click Send as Attachment."

I am wrong?

  • Jul 26, 2013
  • Cid from Brazil
  • Brazil
  • Jul 26, 2013

For the question:
Your customer wants to receive your project's Timeline view in a document by e-mail. You need to create a document that contains only the Timeline view. You select the Timeline view. What should you do next?

The correct answer is:
Select Create PDF/XPS Document.

instead of:
Select Visual Reports.

I am wrong?

  • Jul 26, 2013
  • Cid from Brazil
  • Brazil
  • Jul 26, 2013

For the question:
Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do?

The correct answer is:
Create a named resource for each Standard hourly rate.

instead of:
Create cost tables to include rates that activate on effective dates.

I am wrong?

  • Jul 26, 2013
  • Cid from Brazil
  • Brazil
  • Jul 25, 2013

For the question:
You want to print the Gantt Chart view of your project. You need to hide the Gantt chart legend.
What should you do?

The correct answer is:
Edit the Bar Styles dialog box.

instead of:
Edit the layout.

I am wrong?

  • Jul 25, 2013
  • Cid from Brazil
  • Brazil
  • Jul 25, 2013

For the question:
DRAG DROP
You use Microsoft Project Professional 2010 to manage an engineering project according to the schedule as shown in the exhibit. (Click the Exhibit button.) Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on the first day and informed you that he needs an additional 9 hours of work to finish. You update the schedule. What percentage of units should be reflected in the schedule by Adam's workload? (To answer, drag the appropriate units to the correct locations in the answer area.)

There not reply enable.

I think that is 75% because the task type in the exhibit is "fixed unit".

I am wrong?

  • Jul 25, 2013
  • Cid from Brazil
  • Brazil
  • Jul 25, 2013

For the question:
You need to cancel the Develop prototype based on functional specifications task. You also need to retain all the information from the task. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

The correct answer is:
"Inactivate the task." and "Create a link from the Develop functional specifications task to the Review functional specifications task."
instead of:
"Delete the task." and "Create a link from the Develop functional specifications task to the Review functional specifications task."

I am wrong?

  • Jul 25, 2013
  • Cid from Brazil
  • Brazil
  • Jul 25, 2013

For the question:
You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?

The correct answer is:
Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, and then click OK.
instead of:
Highlight the summary task. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.

I am wrong?

  • Jul 25, 2013
  • Cid from Brazil
  • Brazil
  • Jul 25, 2013

For the question:
You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?

The correct answer is:
Use a cost type resource.
instead of:
Use a work type resource.

I am wrong?

  • Jul 25, 2013
  • Cid from Brazil
  • Brazil
  • Jul 25, 2013

for the question:
You need to create a new project schedule by using tasks from an existing project. You need to achieve this goal without inheriting actual hours from the existing project. What would you do first?

The correct answer is:
Save the task list in Microsoft Excel and use the Project Import Wizard.
instead of:
Open the previously saved project schedule and save it as a template.

I am wrong?

  • Jul 25, 2013
  • Cid from Brazil
  • Brazil
  • Jul 25, 2013

For the question:
You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use?

The correct answer is:
Outdent

I am wrong?

  • Jul 25, 2013
  • Cid from Brazil
  • Brazil
  • Jul 25, 2013

For the question:
The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?
The answer is: Select the Project Summary Task option.
Is not: Create a manually scheduled summary task.
I am wrong?

  • Jul 25, 2013
  • Mr. Projects
  • Malaysia
  • Jul 25, 2013

Don't depend on this dumps only. learn & know your subject is better. the questions is not too tough .i realize there are at least 4-5 question is given a wrong answer.

Anyway, thanks to Ethan for the effort to share this dumps!

  • Jul 25, 2013
  • Anne
  • United States
  • Jul 24, 2013

Has any one cleared this exam with this dump recently.please validate.

  • Jul 24, 2013
  • Bukola
  • Nigeria
  • Jul 24, 2013

Please, i'm nigerian. i want to write this exam tomorrow.
i Hope its valid?
Please,some1 respond

  • Jul 24, 2013
  • Vinu
  • India
  • Jul 15, 2013

Hi Kumar,

How much you scored.is it 100% valid dump

  • Jul 15, 2013
  • Kumar
  • India
  • Jul 15, 2013

Passed the exam today (07/15/2013). If Ethan could give the answer (which percentage to drag and drop on which unit) for the Adam Barr Exhibit question, it would help us to score more.

Special thanks to Ethan for this great help.

  • Jul 15, 2013
  • chandra
  • Poland
  • Jul 13, 2013

Hi,
This dump is valid and yesterday I cleared this exam.

  • Jul 13, 2013

Add Comments

Only Registered Members Can Download VCE Files or View Training Courses

Please fill out your email address below in order to Download VCE files or view Training Courses. Registration is Free and Easy - you simply need to provide an email address.

  • Trusted By 1.2M IT Certification Candidates Every Month
  • VCE Files Simulate Real Exam Environment
  • Instant Download After Registration.
Please provide a correct e-mail address
A confirmation link will be sent to this email address to verify your login.
Already Member? Click Here to Login

Log into your ExamCollection Account

Please Log In to download VCE file or view Training Course

Please provide a correct E-mail address

Please provide your Password (min. 6 characters)

Only registered Examcollection.com members can download vce files or view training courses.

Registration is free and easy - just provide your E-mail address. Click Here to Register

SPECIAL OFFER: GET 10% OFF

ExamCollection Premium

ExamCollection Premium Files

Pass your Exam with ExamCollection's PREMIUM files!

  • ExamCollection Certified Safe Files
  • Guaranteed to have ACTUAL Exam Questions
  • Up-to-Date Exam Study Material - Verified by Experts
  • Instant Downloads
Enter Your Email Address to Receive Your 10% Off Discount Code
A Confirmation Link will be sent to this email address to verify your login
We value your privacy. We will not rent or sell your email address

SPECIAL OFFER: GET 10% OFF

Use Discount Code:

MIN10OFF

A confirmation link was sent to your e-mail.
Please check your mailbox for a message from support@examcollection.com and follow the directions.

Next

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.