Question 840
Before escalating a proposed solution, what should be checked about: Six months after a project closes, the planned benefits review date passes with no actual operational outcome data?
Explanation
Correct Answer
Review the benefits management approach for due dates and owners. Post-project benefit measurement has been neglected after delivery completion. The resulting action would be: Trigger the agreed benefits review with the operational owner and compare results against targets.
Incorrect Answers
Check whether queue-time targets have a current baseline and an accountable beneficiary. That investigation addresses benefit profile lacks measurement owner; for the stated decision, review the benefits management approach for due dates and owners.
Determine when the errors can realistically be measured after deployment. That investigation addresses benefits management timing after closure; for the stated decision, review the benefits management approach for due dates and owners.
Check when and by whom post-launch benefits are measured. That investigation addresses project plan ignores benefits review handover; for the stated decision, review the benefits management approach for due dates and owners.