Question 830
An assurance reviewer investigates: A project manager's end project report says all work is complete, but unresolved minor issues and future benefit reviews have no receiving owner. Which root cause is most consistent with the evidence?
- Administrative closure has severed accountability for residual items
- Product existence has been confused with verified completion
- Planning stops at output delivery even though planned outcomes need operational follow-through
- Expected benefits occur after formal project closure and would otherwise go unverified
Explanation
Correct Answer
A:Administrative closure has severed accountability for residual items. That cause fits the described evidence. The relevant governance rule is: Closing progress information should support controlled transition beyond the project. The appropriate response would be to record accepted follow-on actions and transfer responsibility in the end project report.
Incorrect Answers
B:Product existence has been confused with verified completion. This could explain a different issue concerning product register says complete too early, but the reported conditions instead indicate: Administrative closure has severed accountability for residual items.
C:Planning stops at output delivery even though planned outcomes need operational follow-through. This could explain a different issue concerning project plan ignores benefits review handover, but the reported conditions instead indicate: Administrative closure has severed accountability for residual items.
D:Expected benefits occur after formal project closure and would otherwise go unverified. This could explain a different issue concerning benefits management timing after closure, but the reported conditions instead indicate: Administrative closure has severed accountability for residual items.
Question 831
A product or management action is said to resolve: A project manager's end project report says all work is complete, but unresolved minor issues and future benefit reviews have no receiving owner. Which verification is strongest?
- Operational owners and review dates remain assigned after project closure
- Outstanding actions and benefit reviews have named operational owners and agreed dates
- The relevant operational role accepts a dated benefits review plan
- Product status reflects reviewed acceptance evidence and no mandatory outstanding checks
Explanation
Correct Answer
B:Outstanding actions and benefit reviews have named operational owners and agreed dates. This is the observable outcome expected after the action: Record accepted follow-on actions and transfer responsibility in the end project report. It tests the weakness that administrative closure has severed accountability for residual items.
Incorrect Answers
A:Operational owners and review dates remain assigned after project closure. That would verify benefits management timing after closure, not the outcome at issue. The evidence needed for this situation is: Outstanding actions and benefit reviews have named operational owners and agreed dates.
C:The relevant operational role accepts a dated benefits review plan. That would verify project plan ignores benefits review handover, not the outcome at issue. The evidence needed for this situation is: Outstanding actions and benefit reviews have named operational owners and agreed dates.
D:Product status reflects reviewed acceptance evidence and no mandatory outstanding checks. That would verify product register says complete too early, not the outcome at issue. The evidence needed for this situation is: Outstanding actions and benefit reviews have named operational owners and agreed dates.
Question 832
A board wants to understand the governance reasoning behind addressing: A project manager's end project report says all work is complete, but unresolved minor issues and future benefit reviews have no receiving owner. Which principle best fits?
- Many business benefits are realized in business-as-usual after the delivery project ends
- A product's lifecycle status should correspond to its defined quality and approval state
- Project planning supports transition and realization of intended outcomes after delivery
- Closing progress information should support controlled transition beyond the project
Explanation
Correct Answer
D:Closing progress information should support controlled transition beyond the project. This principle matters here because administrative closure has severed accountability for residual items. The response should tackle the stated project-control deficiency.
Incorrect Answers
A:Many business benefits are realized in business-as-usual after the delivery project ends. That principle is more directly associated with benefits management timing after closure. The present case concerns the weakness that administrative closure has severed accountability for residual items.
B:A product's lifecycle status should correspond to its defined quality and approval state. That principle is more directly associated with product register says complete too early. The present case concerns the weakness that administrative closure has severed accountability for residual items.
C:Project planning supports transition and realization of intended outcomes after delivery. That principle is more directly associated with project plan ignores benefits review handover. The present case concerns the weakness that administrative closure has severed accountability for residual items.
Question 833
The project board asks for a sustainable improvement after: A project manager's end project report says all work is complete, but unresolved minor issues and future benefit reviews have no receiving owner. Which guardrail should be established?
- Integrate benefits-owner handover into planning products
- Use closure acceptance checks for unresolved follow-on items
- Require quality evidence before updating the product register to complete
- Confirm benefit measurement handover in the end project report
Explanation
Correct Answer
B:Use closure acceptance checks for unresolved follow-on items. That preventive control addresses a repeated failure in which administrative closure has severed accountability for residual items. Effectiveness can be checked by: Outstanding actions and benefit reviews have named operational owners and agreed dates.
Incorrect Answers
A:Integrate benefits-owner handover into planning products. It can prevent project plan ignores benefits review handover, but it does not control the stated recurrence risk: Administrative closure has severed accountability for residual items.
C:Require quality evidence before updating the product register to complete. It can prevent product register says complete too early, but it does not control the stated recurrence risk: Administrative closure has severed accountability for residual items.
D:Confirm benefit measurement handover in the end project report. It can prevent benefits management timing after closure, but it does not control the stated recurrence risk: Administrative closure has severed accountability for residual items.
Question 834
For this project problem—A project manager's end project report says all work is complete, but unresolved minor issues and future benefit reviews have no receiving owner—which initial review would most directly focus the response?
- Check when and by whom post-launch benefits are measured
- Determine when the errors can realistically be measured after deployment
- Check the product description's required reviews and completed test records
- Inspect remaining issue register entries and benefit review commitments
Explanation
Correct Answer
D:Inspect remaining issue register entries and benefit review commitments. Administrative closure has severed accountability for residual items. The resulting action would be: Record accepted follow-on actions and transfer responsibility in the end project report.
Incorrect Answers
A:Check when and by whom post-launch benefits are measured. That investigation addresses project plan ignores benefits review handover; for the stated decision, inspect remaining issue register entries and benefit review commitments.
B:Determine when the errors can realistically be measured after deployment. That investigation addresses benefits management timing after closure; for the stated decision, inspect remaining issue register entries and benefit review commitments.
C:Check the product description's required reviews and completed test records. That investigation addresses product register says complete too early; for the stated decision, inspect remaining issue register entries and benefit review commitments.
Question 835
Which response should the responsible project role take for this situation: Six months after a project closes, the planned benefits review date passes with no actual operational outcome data?
- Link post-project benefit measurement responsibility and timing to the project plan and management approaches
- Establish post-project benefit review responsibility and schedule within the benefits management approach
- Trigger the agreed benefits review with the operational owner and compare results against targets
- Define the benefit, its baseline and measurement approach with a named business owner in the benefits management approach
Explanation
Correct Answer
C:Trigger the agreed benefits review with the operational owner and compare results against targets. Post-project benefit measurement has been neglected after delivery completion. Progress controls should provide for evaluating outcomes after project completion.
Incorrect Answers
A:Link post-project benefit measurement responsibility and timing to the project plan and management approaches. It applies to project plan ignores benefits review handover; the current decision depends on this finding: Post-project benefit measurement has been neglected after delivery completion.
B:Establish post-project benefit review responsibility and schedule within the benefits management approach. It applies to benefits management timing after closure; the current decision depends on this finding: Post-project benefit measurement has been neglected after delivery completion.
D:Define the benefit, its baseline and measurement approach with a named business owner in the benefits management approach. It applies to benefit profile lacks measurement owner; the current decision depends on this finding: Post-project benefit measurement has been neglected after delivery completion.
Question 836
The project has the following difficulty: Six months after a project closes, the planned benefits review date passes with no actual operational outcome data. What underlying management failure best explains it?
- Expected benefits occur after formal project closure and would otherwise go unverified
- Planning stops at output delivery even though planned outcomes need operational follow-through
- Post-project benefit measurement has been neglected after delivery completion
- A projected outcome is not tied to measurable post-project accountability
Explanation
Correct Answer
C:Post-project benefit measurement has been neglected after delivery completion. That cause fits the described evidence. The relevant governance rule is: Progress controls should provide for evaluating outcomes after project completion. The appropriate response would be to trigger the agreed benefits review with the operational owner and compare results against targets.
Incorrect Answers
A:Expected benefits occur after formal project closure and would otherwise go unverified. This could explain a different issue concerning benefits management timing after closure, but the reported conditions instead indicate: Post-project benefit measurement has been neglected after delivery completion.
B:Planning stops at output delivery even though planned outcomes need operational follow-through. This could explain a different issue concerning project plan ignores benefits review handover, but the reported conditions instead indicate: Post-project benefit measurement has been neglected after delivery completion.
D:A projected outcome is not tied to measurable post-project accountability. This could explain a different issue concerning benefit profile lacks measurement owner, but the reported conditions instead indicate: Post-project benefit measurement has been neglected after delivery completion.
Question 837
The project board requests closure evidence for this issue: Six months after a project closes, the planned benefits review date passes with no actual operational outcome data. Which observation best supports approval?
- Operational owners and review dates remain assigned after project closure
- The relevant operational role accepts a dated benefits review plan
- The benefits management approach identifies owner, baseline, target and review date for queue time
- The accountable owner reports actual benefits and reasons for variance
Explanation
Correct Answer
D:The accountable owner reports actual benefits and reasons for variance. This is the observable outcome expected after the action: Trigger the agreed benefits review with the operational owner and compare results against targets. It tests the weakness that post-project benefit measurement has been neglected after delivery completion.
Incorrect Answers
A:Operational owners and review dates remain assigned after project closure. That would verify benefits management timing after closure, not the outcome at issue. The evidence needed for this situation is: The accountable owner reports actual benefits and reasons for variance.
B:The relevant operational role accepts a dated benefits review plan. That would verify project plan ignores benefits review handover, not the outcome at issue. The evidence needed for this situation is: The accountable owner reports actual benefits and reasons for variance.
C:The benefits management approach identifies owner, baseline, target and review date for queue time. That would verify benefit profile lacks measurement owner, not the outcome at issue. The evidence needed for this situation is: The accountable owner reports actual benefits and reasons for variance.
Question 838
For the project situation—Six months after a project closes, the planned benefits review date passes with no actual operational outcome data—which underlying method concept should guide the decision?
- Benefit realization needs accountability and measurement beyond acceptance of a technical product
- Progress controls should provide for evaluating outcomes after project completion
- Project planning supports transition and realization of intended outcomes after delivery
- Many business benefits are realized in business-as-usual after the delivery project ends
Explanation
Correct Answer
B:Progress controls should provide for evaluating outcomes after project completion. This principle matters here because post-project benefit measurement has been neglected after delivery completion. The response should tackle the stated project-control deficiency.
Incorrect Answers
A:Benefit realization needs accountability and measurement beyond acceptance of a technical product. That principle is more directly associated with benefit profile lacks measurement owner. The present case concerns the weakness that post-project benefit measurement has been neglected after delivery completion.
C:Project planning supports transition and realization of intended outcomes after delivery. That principle is more directly associated with project plan ignores benefits review handover. The present case concerns the weakness that post-project benefit measurement has been neglected after delivery completion.
D:Many business benefits are realized in business-as-usual after the delivery project ends. That principle is more directly associated with benefits management timing after closure. The present case concerns the weakness that post-project benefit measurement has been neglected after delivery completion.
Question 839
What ongoing assurance step best addresses the recurring risk seen here: Six months after a project closes, the planned benefits review date passes with no actual operational outcome data?
- Integrate benefits-owner handover into planning products
- Validate benefits measures and owners with the senior user at major decision points
- Monitor post-project review commitments in portfolio or business-as-usual governance
- Confirm benefit measurement handover in the end project report
Explanation
Correct Answer
C:Monitor post-project review commitments in portfolio or business-as-usual governance. That preventive control addresses a repeated failure in which post-project benefit measurement has been neglected after delivery completion. Effectiveness can be checked by: The accountable owner reports actual benefits and reasons for variance.
Incorrect Answers
A:Integrate benefits-owner handover into planning products. It can prevent project plan ignores benefits review handover, but it does not control the stated recurrence risk: Post-project benefit measurement has been neglected after delivery completion.
B:Validate benefits measures and owners with the senior user at major decision points. It can prevent benefit profile lacks measurement owner, but it does not control the stated recurrence risk: Post-project benefit measurement has been neglected after delivery completion.
D:Confirm benefit measurement handover in the end project report. It can prevent benefits management timing after closure, but it does not control the stated recurrence risk: Post-project benefit measurement has been neglected after delivery completion.
Question 840
Before escalating a proposed solution, what should be checked about: Six months after a project closes, the planned benefits review date passes with no actual operational outcome data?
- Check whether queue-time targets have a current baseline and an accountable beneficiary
- Determine when the errors can realistically be measured after deployment
- Check when and by whom post-launch benefits are measured
- Review the benefits management approach for due dates and owners
Explanation
Correct Answer
D:Review the benefits management approach for due dates and owners. Post-project benefit measurement has been neglected after delivery completion. The resulting action would be: Trigger the agreed benefits review with the operational owner and compare results against targets.
Incorrect Answers
A:Check whether queue-time targets have a current baseline and an accountable beneficiary. That investigation addresses benefit profile lacks measurement owner; for the stated decision, review the benefits management approach for due dates and owners.
B:Determine when the errors can realistically be measured after deployment. That investigation addresses benefits management timing after closure; for the stated decision, review the benefits management approach for due dates and owners.
C:Check when and by whom post-launch benefits are measured. That investigation addresses project plan ignores benefits review handover; for the stated decision, review the benefits management approach for due dates and owners.
PRINCE2 7 Practitioner Practice Tests