Question 850
Which PRINCE2 management principle or mechanism best explains the appropriate response to: The project manager wants to proceed directly from a project mandate to detailed plans without checking an earlier failed rollout of the same service?
Explanation
Correct Answer
Starting up should use experience before substantial initiation effort is authorized. This principle matters here because reusable experience is being omitted from the first feasibility decisions. The response should tackle the stated project-control deficiency.
Incorrect Answers
Stage boundaries are opportunities to learn before the next investment decision. That principle is more directly associated with stage report omits lessons. The present case concerns the weakness that reusable experience is being omitted from the first feasibility decisions.
Controlling a stage includes managing risks when information changes. That principle is more directly associated with risk warning ignored until stage end. The present case concerns the weakness that reusable experience is being omitted from the first feasibility decisions.
Managing product delivery contributes progress and learning information to the project manager. That principle is more directly associated with team records lessons too late. The present case concerns the weakness that reusable experience is being omitted from the first feasibility decisions.