Question 820
During application of PRINCE2 7, what governing idea is illustrated by: A supplier reports sixty percent completion using its own work units that cannot be reconciled with work package products or stage milestones?
Explanation
Correct Answer
Team-level progress must be meaningful to the project manager's stage control. This principle matters here because the checkpoint uses a metric disconnected from authorized plans. The response should tackle the stated project-control deficiency.
Incorrect Answers
Issues include problems or concerns as well as requests and off-specifications. That principle is more directly associated with problem cannot be assigned to product change. The present case concerns the weakness that the checkpoint uses a metric disconnected from authorized plans.
Not every issue is an exception; escalation depends on forecast authority limits. That principle is more directly associated with urgent issue confused with exception. The present case concerns the weakness that the checkpoint uses a metric disconnected from authorized plans.
Plans must share coherent assumptions for integration and control. That principle is more directly associated with schedules use inconsistent units. The present case concerns the weakness that the checkpoint uses a metric disconnected from authorized plans.



PRINCE2 7 Practitioner Practice Tests