Question 800
The project has the following difficulty: After a stage is forecast outside tolerance, the project manager asks the team to execute a revised plan before the board approves it. What underlying management failure best explains it?
Explanation
Correct Answer
A replacement baseline has been used without authorized exception direction. That cause fits the described evidence. The relevant governance rule is: Exception plans are subject to the same governance authorization as the plan they replace. The appropriate response would be to submit the proposed exception plan for the correct authorization and preserve control meanwhile.
Incorrect Answers
An issue's urgency is being mistaken for a tolerance exception. This could explain a different issue concerning urgent issue confused with exception, but the reported conditions instead indicate: A replacement baseline has been used without authorized exception direction.
A normal in-tolerance adjustment has been mistaken for an exception condition. This could explain a different issue concerning exception plan drafted for normal variance, but the reported conditions instead indicate: A replacement baseline has been used without authorized exception direction.
Delivery accountability is being confused with direction of project objectives. This could explain a different issue concerning team manager signs board strategy, but the reported conditions instead indicate: A replacement baseline has been used without authorized exception direction.