Question 790
Which general PRINCE2 control concept is most pertinent to this problem: At a stage boundary the project manager sends financial actuals but omits updated benefit assumptions and major risks?
Explanation
Correct Answer
Stage boundary reporting informs whether continued investment is warranted. This principle matters here because the board lacks balanced information to decide on further investment. The response should tackle the stated project-control deficiency.
Incorrect Answers
A project brief supports the starting-up decision before detailed initiation products exist. That principle is more directly associated with unclear project brief at authorization. The present case concerns the weakness that the board lacks balanced information to decide on further investment.
The executive leads business justification while the project manager manages authorized work. That principle is more directly associated with executive delegates investment decision downwards. The present case concerns the weakness that the board lacks balanced information to decide on further investment.
Risk assessments should evolve as evidence accumulates. That principle is more directly associated with probability changes after pilot. The present case concerns the weakness that the board lacks balanced information to decide on further investment.