Question 770
A team reflects on this failure: The project manager keeps a lessons log blank until the end despite recurring supplier coordination problems. What is the most relevant underlying problem?
Explanation
Correct Answer
Learning has been postponed until it can no longer affect delivery. That cause fits the described evidence. The relevant governance rule is: Progress management includes recording and applying lessons throughout delivery. The appropriate response would be to record lessons as they occur and apply relevant actions in current or next stages.
Incorrect Answers
The investment analysis no longer reflects the committed acquisition cost. This could explain a different issue concerning viability after supplier price increase, but the reported conditions instead indicate: Learning has been postponed until it can no longer affect delivery.
The assurance function cannot inform the body accountable for direction. This could explain a different issue concerning project assurance reports only to supplier, but the reported conditions instead indicate: Learning has been postponed until it can no longer affect delivery.
Delivery has been delegated without explicit acceptance and control terms. This could explain a different issue concerning work package lacks quality responsibilities, but the reported conditions instead indicate: Learning has been postponed until it can no longer affect delivery.