Question 760
A board wants to understand the governance reasoning behind addressing: A team manager misses two agreed checkpoint reports, leaving the project manager unable to forecast the work package finish. Which principle best fits?
Explanation
Correct Answer
Checkpoint reporting supports monitoring of delegated delivery. This principle matters here because the agreed team-level progress control is not being performed. The response should tackle the stated project-control deficiency.
Incorrect Answers
Defined roles separate strategic direction, day-to-day project management and product delivery. That principle is more directly associated with team manager signs board strategy. The present case concerns the weakness that the agreed team-level progress control is not being performed.
Off-specifications are issues requiring a managed decision on deviation or correction. That principle is more directly associated with off-specification not recorded. The present case concerns the weakness that the agreed team-level progress control is not being performed.
Quality assurance and quality control have different objectives and cannot substitute for one another. That principle is more directly associated with quality assurance independent of project. The present case concerns the weakness that the agreed team-level progress control is not being performed.