Question 740
Which diagnosis best fits the project scenario: A stage manager sends every typo correction as a formal project board decision despite delegated local issue controls?
Explanation
Correct Answer
Decision processes are not being tailored to significance and authority. That cause fits the described evidence. The relevant governance rule is: Proportionate issue control protects governance attention while retaining traceability. The appropriate response would be to handle low-impact issues under the agreed delegated process and summarize as appropriate.
Incorrect Answers
The business investment decision is being pushed below the board's mandate. This could explain a different issue concerning executive delegates investment decision downwards, but the reported conditions instead indicate: Decision processes are not being tailored to significance and authority.
Routine reporting is being used to mask a breach of delegated authority. This could explain a different issue concerning highlight report hides forecast exception, but the reported conditions instead indicate: Decision processes are not being tailored to significance and authority.
A threat to project viability exceeds the authority of routine stage controls. This could explain a different issue concerning escalating project-level strategic risk, but the reported conditions instead indicate: Decision processes are not being tailored to significance and authority.