Question 720
Before changing its management arrangements, the project team observes: A major supplier problem can be corrected without exceeding any tolerance, but the project manager submits a stage exception plan immediately. What is the most useful first check?
Explanation
Correct Answer
Calculate the impact of the issue on current stage and project tolerances. An issue's urgency is being mistaken for a tolerance exception. The resulting action would be: Control the issue within delegated authority and escalate only if forecast tolerances will be exceeded.
Incorrect Answers
Compare audit findings with required product test results. That investigation addresses quality assurance independent of project; for the stated decision, examine calculate the impact of the issue on current stage and project tolerances.
Calculate the forecast finish date relative to stage tolerance. That investigation addresses exception plan drafted for normal variance; for the stated decision, examine calculate the impact of the issue on current stage and project tolerances.
Check who signed the supplier change instruction. That investigation addresses pmo confused with project manager; for the stated decision, examine calculate the impact of the issue on current stage and project tolerances.