Question 700
An instructor asks why the proposed management control is justified for: An issue report recommends a costly vendor replacement but lists no alternatives or assessed implications. Which explanation is most relevant?
Explanation
Correct Answer
Issue reporting should support informed decisions rather than merely record preferred solutions. This principle matters here because decision makers cannot compare the proposed solution with feasible alternatives. The response should tackle the stated project-control deficiency.
Incorrect Answers
Commercial arrangements should be incorporated into the project management team structure. That principle is more directly associated with commercial responsibility unclear. The present case concerns the weakness that decision makers cannot compare the proposed solution with feasible alternatives.
Team-level progress must be meaningful to the project manager's stage control. That principle is more directly associated with checkpoint progress inconsistent with stage plan. The present case concerns the weakness that decision makers cannot compare the proposed solution with feasible alternatives.
The executive is accountable for business justification, not for bypassing it. That principle is more directly associated with executive sponsors a favored option. The present case concerns the weakness that decision makers cannot compare the proposed solution with feasible alternatives.