Question 730
For the project situation—Two delivery partners blame each other for a missed interface contract and the issue log has no assigned action owner—which underlying method concept should guide the decision?
Explanation
Correct Answer
Effective issue control links each problem to ownership and a decision route. This principle matters here because ambiguous cross-supplier accountability is preventing issue resolution. The response should tackle the stated project-control deficiency.
Incorrect Answers
Quality management approaches should define consistent controls appropriate to product risk. That principle is more directly associated with inspection effort inconsistent across suppliers. The present case concerns the weakness that ambiguous cross-supplier accountability is preventing issue resolution.
Project assurance supports board confidence without becoming a substitute for project management. That principle is more directly associated with project assurance reports only to supplier. The present case concerns the weakness that ambiguous cross-supplier accountability is preventing issue resolution.
Risk responses must have accountable ownership and operational follow-through. That principle is more directly associated with threat response assigned without accountability. The present case concerns the weakness that ambiguous cross-supplier accountability is preventing issue resolution.