Question 70
Which general PRINCE2 control concept is most pertinent to this problem: A project divides implementation by software components only, even though the board needs a separate decision before a high-risk procurement commitment?
Explanation
Correct Answer
A management stage is primarily a governance and authorization interval. This principle matters here because technical architecture phases have been mistaken for investment-control stages. The response should tackle the stated project-control deficiency.
Incorrect Answers
Tailoring adapts the method to context rather than abandoning its governance intent. That principle is more directly associated with tiny internal project buried in paperwork. The present case concerns the weakness that technical architecture phases have been mistaken for investment-control stages.
A team manager escalates forecast breaches of a work package's delegated tolerances. That principle is more directly associated with team forecast outside work package. The present case concerns the weakness that technical architecture phases have been mistaken for investment-control stages.
Project assurance supports the project board without replacing the project manager's delivery control. That principle is more directly associated with independent assurance of technical claims. The present case concerns the weakness that technical architecture phases have been mistaken for investment-control stages.



PRINCE2 7 Practitioner Practice Tests