Question 60
A project manager must triage the following issue: A team is ordered to produce task-level schedules for all three years of a rapidly changing technology project before the first stage has produced any evidence. What initial investigation best distinguishes the causes?
Explanation
Correct Answer
Check how reliable the later-stage estimates really are versus the current stage. Long-horizon uncertainty is being disguised by an unrealistic level of detail. The resulting action would be: Plan the immediate management stage in detail while maintaining a higher-level overall project plan.
Incorrect Answers
Ask for the project's product description and acceptance criteria. That investigation addresses activities scheduled without acceptance criteria; for the stated decision, check how reliable the later-stage estimates really are versus the current stage.
Read the work package description for acceptance criteria, tolerances and change authority. That investigation addresses unclear team manager authority; for the stated decision, check how reliable the later-stage estimates really are versus the current stage.
Inspect the work package tolerance and the latest delivery forecast. That investigation addresses team forecast outside work package; for the stated decision, check how reliable the later-stage estimates really are versus the current stage.