Question 50
A team reflects on this failure: A supplier's own engineering manager signs off product quality as project assurance even though the project board lacks any independent visibility of technical risks. What is the most relevant underlying problem?
Explanation
Correct Answer
Product delivery self-certification has been substituted for board-level assurance. That cause fits the described evidence. The relevant governance rule is: Project assurance supports the project board without replacing the project manager's delivery control. The appropriate response would be to assign assurance reporting on the supplier perspective independently of delivery ownership.
Incorrect Answers
Forecast breach of delegated tolerance has not triggered the required higher-level decision. This could explain a different issue concerning forecast stage cost exceeds tolerance, but the reported conditions instead indicate: Product delivery self-certification has been substituted for board-level assurance.
Technical architecture phases have been mistaken for investment-control stages. This could explain a different issue concerning management stages versus technical phases, but the reported conditions instead indicate: Product delivery self-certification has been substituted for board-level assurance.
Delegated team-level limits have been ignored even though the breach is forecast. This could explain a different issue concerning team forecast outside work package, but the reported conditions instead indicate: Product delivery self-certification has been substituted for board-level assurance.