Question 90
Which first piece of evidence best helps understand this situation: A minor adjustment fits every permitted stage tolerance and complies with the approved change procedure, but the project manager asks the board to make every operational decision?
Explanation
Correct Answer
Test whether the proposed adjustment actually breaches a relevant tolerance. Over-escalation is defeating the management-by-exception delegation. The resulting action would be: Act within delegated authority and report through normal controls rather than escalating routine matters.
Incorrect Answers
Compare legal compliance demands with the proposed control and documentation set. That investigation addresses regulated transformation with casual governance; for the stated decision, examine test whether the proposed adjustment actually breaches a relevant tolerance.
Check whether the current stage's completion and the next-stage plan were reviewed by the board. That investigation addresses stage transition without board decision; for the stated decision, examine test whether the proposed adjustment actually breaches a relevant tolerance.
Read the work package description for acceptance criteria, tolerances and change authority. That investigation addresses unclear team manager authority; for the stated decision, examine test whether the proposed adjustment actually breaches a relevant tolerance.