PRINCE2 7 Practitioner Bundle gives you unlimited access to "PRINCE2 7 Practitioner" files. However, this does not replace the need for a .vce exam simulator. To download VCE exam simulator click here
PRINCE2 7 Practitioner Premium VCE File
PRINCE2 PRINCE2 7 Practitioner Premium File

93 Questions & Answers

Last Update: Nov 02, 2026

$69.99

PRINCE2 PRINCE2 7 Practitioner Exam Bundle gives you unlimited access to "PRINCE2 7 Practitioner" files. However, this does not replace the need for a .vce exam simulator. To download your .vce exam simulator click here

PRINCE2 PRINCE2 7 Practitioner Practice Test 118

Question 1170

Which first piece of evidence best helps understand this situation: The manager submits a closure request with a list of delivered products but no comparison with approved time, cost, quality or business objectives?

  1. Compare actual product acceptance and costs with project plan commitments
  2. Compare remaining supplier commitments and work with budget headroom
  3. Identify the effect of the proposed extension on the stage critical path
  4. Inspect whether the request includes scope, quality and progress controls

Explanation

Correct Answer

A:

Compare actual product acceptance and costs with project plan commitments. Closure governance lacks the overall performance evaluation. The resulting action would be: Prepare an end project report assessing actual outcomes against the project's approved baselines.

Incorrect Answers

B:

Compare remaining supplier commitments and work with budget headroom. That investigation addresses actual costs mask forecast overspend; for the stated decision, compare actual product acceptance and costs with project plan commitments.

C:

Identify the effect of the proposed extension on the stage critical path. That investigation addresses team plan conflicts with main stage; for the stated decision, compare actual product acceptance and costs with project plan commitments.

D:

Inspect whether the request includes scope, quality and progress controls. That investigation addresses team starts work without agreement; for the stated decision, compare actual product acceptance and costs with project plan commitments.

Question 1171

A delivery lead describes this project difficulty: The project relies on a specialist contractor who has solved recurring problems, but the contractor's contract ends before lessons are captured. Which response best fits the method?

  1. Review relevant previous lessons during starting up and reflect them in the project brief and initiation stage plan
  2. Exercise ad hoc direction to review justification and decide whether to continue, redirect or close
  3. Summarize relevant lessons and actions with the stage-boundary report
  4. Produce an actionable lessons report and retain the knowledge before contract exit

Explanation

Correct Answer

D:

Produce an actionable lessons report and retain the knowledge before contract exit. Project learning depends on personnel who are about to leave. Closing should preserve experience for future projects and operations.

Incorrect Answers

A:

Review relevant previous lessons during starting up and reflect them in the project brief and initiation stage plan. It applies to early lessons from similar initiative; the current decision depends on this finding: Project learning depends on personnel who are about to leave.

B:

Exercise ad hoc direction to review justification and decide whether to continue, redirect or close. It applies to business justification withdrawn midstage; the current decision depends on this finding: Project learning depends on personnel who are about to leave.

C:

Summarize relevant lessons and actions with the stage-boundary report. It applies to stage report omits lessons; the current decision depends on this finding: Project learning depends on personnel who are about to leave.

Question 1172

Which diagnosis best fits the project scenario: The project relies on a specialist contractor who has solved recurring problems, but the contractor's contract ends before lessons are captured?

  1. Project learning depends on personnel who are about to leave
  2. Reusable experience is being omitted from the first feasibility decisions
  3. Direction is being delayed even though the project's ongoing rationale is in doubt
  4. Organizational learning is being separated from planned future stage work

Explanation

Correct Answer

A:

Project learning depends on personnel who are about to leave. That cause fits the described evidence. The relevant governance rule is: Closing should preserve experience for future projects and operations. The appropriate response would be to produce an actionable lessons report and retain the knowledge before contract exit.

Incorrect Answers

B:

Reusable experience is being omitted from the first feasibility decisions. This could explain a different issue concerning early lessons from similar initiative, but the reported conditions instead indicate: Project learning depends on personnel who are about to leave.

C:

Direction is being delayed even though the project's ongoing rationale is in doubt. This could explain a different issue concerning business justification withdrawn midstage, but the reported conditions instead indicate: Project learning depends on personnel who are about to leave.

D:

Organizational learning is being separated from planned future stage work. This could explain a different issue concerning stage report omits lessons, but the reported conditions instead indicate: Project learning depends on personnel who are about to leave.

Question 1173

In a project health review, what outcome would validate resolution of: The project relies on a specialist contractor who has solved recurring problems, but the contractor's contract ends before lessons are captured?

  1. A timely board decision addresses the changed external mandate
  2. The next stage plan reflects documented lessons from the preceding stage
  3. The organization receives a validated lessons report with transferable recommendations
  4. Early planning includes responses to documented historic adoption failures

Explanation

Correct Answer

C:

The organization receives a validated lessons report with transferable recommendations. This is the observable outcome expected after the action: Produce an actionable lessons report and retain the knowledge before contract exit. It tests the weakness that project learning depends on personnel who are about to leave.

Incorrect Answers

A:

A timely board decision addresses the changed external mandate. That would verify business justification withdrawn midstage, not the outcome at issue. The evidence needed for this situation is: The organization receives a validated lessons report with transferable recommendations.

B:

The next stage plan reflects documented lessons from the preceding stage. That would verify stage report omits lessons, not the outcome at issue. The evidence needed for this situation is: The organization receives a validated lessons report with transferable recommendations.

D:

Early planning includes responses to documented historic adoption failures. That would verify early lessons from similar initiative, not the outcome at issue. The evidence needed for this situation is: The organization receives a validated lessons report with transferable recommendations.

Question 1174

Which PRINCE2 management principle or mechanism best explains the appropriate response to: The project relies on a specialist contractor who has solved recurring problems, but the contractor's contract ends before lessons are captured?

  1. Stage boundaries are opportunities to learn before the next investment decision
  2. Starting up should use experience before substantial initiation effort is authorized
  3. Closing should preserve experience for future projects and operations
  4. The board can direct the project between formal stage decisions when material circumstances change

Explanation

Correct Answer

C:

Closing should preserve experience for future projects and operations. This principle matters here because project learning depends on personnel who are about to leave. The response should tackle the stated project-control deficiency.

Incorrect Answers

A:

Stage boundaries are opportunities to learn before the next investment decision. That principle is more directly associated with stage report omits lessons. The present case concerns the weakness that project learning depends on personnel who are about to leave.

B:

Starting up should use experience before substantial initiation effort is authorized. That principle is more directly associated with early lessons from similar initiative. The present case concerns the weakness that project learning depends on personnel who are about to leave.

D:

The board can direct the project between formal stage decisions when material circumstances change. That principle is more directly associated with business justification withdrawn midstage. The present case concerns the weakness that project learning depends on personnel who are about to leave.

Question 1175

A lessons review covers: The project relies on a specialist contractor who has solved recurring problems, but the contractor's contract ends before lessons are captured. What future working practice should be adopted?

  1. Establish trigger points for extraordinary justification reviews
  2. Include a lessons review in startup activities
  3. Include supplier lesson handover in exit agreements
  4. Require lessons-log review in boundary planning

Explanation

Correct Answer

C:

Include supplier lesson handover in exit agreements. That preventive control addresses a repeated failure in which project learning depends on personnel who are about to leave. Effectiveness can be checked by: The organization receives a validated lessons report with transferable recommendations.

Incorrect Answers

A:

Establish trigger points for extraordinary justification reviews. It can prevent business justification withdrawn midstage, but it does not control the stated recurrence risk: Project learning depends on personnel who are about to leave.

B:

Include a lessons review in startup activities. It can prevent early lessons from similar initiative, but it does not control the stated recurrence risk: Project learning depends on personnel who are about to leave.

D:

Require lessons-log review in boundary planning. It can prevent stage report omits lessons, but it does not control the stated recurrence risk: Project learning depends on personnel who are about to leave.

Question 1176

A project manager must triage the following issue: The project relies on a specialist contractor who has solved recurring problems, but the contractor's contract ends before lessons are captured. What initial investigation best distinguishes the causes?

  1. Locate the last similar project's lessons report
  2. Examine lessons captured from supplier procurement and handover
  3. Interview departing specialists about repeated defects and effective responses
  4. Verify the policy change and business case dependency it affects

Explanation

Correct Answer

C:

Interview departing specialists about repeated defects and effective responses. Project learning depends on personnel who are about to leave. The resulting action would be: Produce an actionable lessons report and retain the knowledge before contract exit.

Incorrect Answers

A:

Locate the last similar project's lessons report. That investigation addresses early lessons from similar initiative; for the stated decision, examine interview departing specialists about repeated defects and effective responses.

B:

Examine lessons captured from supplier procurement and handover. That investigation addresses stage report omits lessons; for the stated decision, examine interview departing specialists about repeated defects and effective responses.

D:

Verify the policy change and business case dependency it affects. That investigation addresses business justification withdrawn midstage; for the stated decision, examine interview departing specialists about repeated defects and effective responses.

Question 1177

A project board needs to respond to the following situation: Five low-severity issues remain unresolved at project acceptance, but the team removes them from the log to close quickly. Which next action is strongest?

  1. Agree and assign follow-on action ownership and include it in closure documentation
  2. Summarize relevant lessons and actions with the stage-boundary report
  3. Require evidence of acceptance and outstanding action disposition before authorizing closure
  4. Raise the proposed change through the agreed issue/work package route instead of altering the target alone

Explanation

Correct Answer

A:

Agree and assign follow-on action ownership and include it in closure documentation. Project closure is being achieved by hiding residual obligations. Closure can transfer accepted residual actions rather than pretend none exist.

Incorrect Answers

B:

Summarize relevant lessons and actions with the stage-boundary report. It applies to stage report omits lessons; the current decision depends on this finding: Project closure is being achieved by hiding residual obligations.

C:

Require evidence of acceptance and outstanding action disposition before authorizing closure. It applies to closure decision without user evidence; the current decision depends on this finding: Project closure is being achieved by hiding residual obligations.

D:

Raise the proposed change through the agreed issue/work package route instead of altering the target alone. It applies to team manager changes acceptance criteria; the current decision depends on this finding: Project closure is being achieved by hiding residual obligations.

Question 1178

A stage review identifies: Five low-severity issues remain unresolved at project acceptance, but the team removes them from the log to close quickly. Which weakness in control or decision-making is most likely?

  1. Project closure is being achieved by hiding residual obligations
  2. Organizational learning is being separated from planned future stage work
  3. A board decision would terminate governance without validating completion and handover
  4. Delivery discretion is being used to change baselined requirements

Explanation

Correct Answer

A:

Project closure is being achieved by hiding residual obligations. That cause fits the described evidence. The relevant governance rule is: Closure can transfer accepted residual actions rather than pretend none exist. The appropriate response would be to agree and assign follow-on action ownership and include it in closure documentation.

Incorrect Answers

B:

Organizational learning is being separated from planned future stage work. This could explain a different issue concerning stage report omits lessons, but the reported conditions instead indicate: Project closure is being achieved by hiding residual obligations.

C:

A board decision would terminate governance without validating completion and handover. This could explain a different issue concerning closure decision without user evidence, but the reported conditions instead indicate: Project closure is being achieved by hiding residual obligations.

D:

Delivery discretion is being used to change baselined requirements. This could explain a different issue concerning team manager changes acceptance criteria, but the reported conditions instead indicate: Project closure is being achieved by hiding residual obligations.

Question 1179

An assurance reviewer is testing the response to: Five low-severity issues remain unresolved at project acceptance, but the team removes them from the log to close quickly. Which result should be checked?

  1. Each remaining issue has an accepted owner and planned resolution after closure
  2. The final product meets the approved criterion or has a properly authorized change
  3. The board's closure decision is supported by acceptance and follow-on evidence
  4. The next stage plan reflects documented lessons from the preceding stage

Explanation

Correct Answer

A:

Each remaining issue has an accepted owner and planned resolution after closure. This is the observable outcome expected after the action: Agree and assign follow-on action ownership and include it in closure documentation. It tests the weakness that project closure is being achieved by hiding residual obligations.

Incorrect Answers

B:

The final product meets the approved criterion or has a properly authorized change. That would verify team manager changes acceptance criteria, not the outcome at issue. The evidence needed for this situation is: Each remaining issue has an accepted owner and planned resolution after closure.

C:

The board's closure decision is supported by acceptance and follow-on evidence. That would verify closure decision without user evidence, not the outcome at issue. The evidence needed for this situation is: Each remaining issue has an accepted owner and planned resolution after closure.

D:

The next stage plan reflects documented lessons from the preceding stage. That would verify stage report omits lessons, not the outcome at issue. The evidence needed for this situation is: Each remaining issue has an accepted owner and planned resolution after closure.

Question 1180

During application of PRINCE2 7, what governing idea is illustrated by: Five low-severity issues remain unresolved at project acceptance, but the team removes them from the log to close quickly?

  1. Team managers deliver agreed products rather than set unapproved project requirements
  2. Stage boundaries are opportunities to learn before the next investment decision
  3. Closure can transfer accepted residual actions rather than pretend none exist
  4. Directing a project includes authorization to close on a defensible completion basis

Explanation

Correct Answer

C:

Closure can transfer accepted residual actions rather than pretend none exist. This principle matters here because project closure is being achieved by hiding residual obligations. The response should tackle the stated project-control deficiency.

Incorrect Answers

A:

Team managers deliver agreed products rather than set unapproved project requirements. That principle is more directly associated with team manager changes acceptance criteria. The present case concerns the weakness that project closure is being achieved by hiding residual obligations.

B:

Stage boundaries are opportunities to learn before the next investment decision. That principle is more directly associated with stage report omits lessons. The present case concerns the weakness that project closure is being achieved by hiding residual obligations.

D:

Directing a project includes authorization to close on a defensible completion basis. That principle is more directly associated with closure decision without user evidence. The present case concerns the weakness that project closure is being achieved by hiding residual obligations.


PRINCE2 7 Practitioner Practice Tests

Purchase Individually

PRINCE2 7 Practitioner Premium File

Premium File
PRINCE2 7 Practitioner Premium File
93 Q&A
$76.99$69.99

Site Search:

 

VISA, MasterCard, AmericanExpress, UnionPay

SPECIAL OFFER: GET 10% OFF

ExamCollection Premium

ExamCollection Premium Files

Pass your Exam with ExamCollection's PREMIUM files!

  • ExamCollection Certified Safe Files
  • Guaranteed to have ACTUAL Exam Questions
  • Up-to-Date Exam Study Material - Verified by Experts
  • Instant Downloads
Enter Your Email Address to Receive Your 10% Off Discount Code
A Confirmation Link will be sent to this email address to verify your login
We value your privacy. We will not rent or sell your email address

SPECIAL OFFER: GET 10% OFF

Use Discount Code:

MIN10OFF

A confirmation link was sent to your e-mail.
Please check your mailbox for a message from support@examcollection.com and follow the directions.

Next

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.