PRINCE2 7 Practitioner Bundle gives you unlimited access to "PRINCE2 7 Practitioner" files. However, this does not replace the need for a .vce exam simulator. To download VCE exam simulator click here
PRINCE2 7 Practitioner Premium VCE File
PRINCE2 PRINCE2 7 Practitioner Premium File

93 Questions & Answers

Last Update: Nov 02, 2026

$69.99

PRINCE2 PRINCE2 7 Practitioner Exam Bundle gives you unlimited access to "PRINCE2 7 Practitioner" files. However, this does not replace the need for a .vce exam simulator. To download your .vce exam simulator click here

PRINCE2 PRINCE2 7 Practitioner Practice Test 116

Question 1150

Which general PRINCE2 control concept is most pertinent to this problem: The manager warns of a forthcoming cost exception at the boundary but provides no alternative responses or assessment of continuing value?

  1. Routine progress communication and exceptional escalation are complementary controls
  2. Directing a project includes a distinct decision to authorize the project
  3. Exception handling should give decision makers assessed options rather than only bad news
  4. Starting up tests whether a project appears worthwhile before major resources are spent

Explanation

Correct Answer

C:

Exception handling should give decision makers assessed options rather than only bad news. This principle matters here because the board has been alerted to a problem without decision-supporting analysis. The response should tackle the stated project-control deficiency.

Incorrect Answers

A:

Routine progress communication and exceptional escalation are complementary controls. That principle is more directly associated with stage highlight report omitted. The present case concerns the weakness that the board has been alerted to a problem without decision-supporting analysis.

B:

Directing a project includes a distinct decision to authorize the project. That principle is more directly associated with project manager self-authorizes project. The present case concerns the weakness that the board has been alerted to a problem without decision-supporting analysis.

D:

Starting up tests whether a project appears worthwhile before major resources are spent. That principle is more directly associated with outline business case has no outcome. The present case concerns the weakness that the board has been alerted to a problem without decision-supporting analysis.

Question 1151

After an effective correction, which management improvement best prevents a repeat of: The manager warns of a forthcoming cost exception at the boundary but provides no alternative responses or assessment of continuing value?

  1. Set reporting frequency in the stage plan and monitor compliance
  2. Require an initial business justification at project entry
  3. Include options and recommendation in exception planning templates
  4. Enforce procurement approval gates aligned with board authorization

Explanation

Correct Answer

C:

Include options and recommendation in exception planning templates. That preventive control addresses a repeated failure in which the board has been alerted to a problem without decision-supporting analysis. Effectiveness can be checked by: Direction can compare recovery, scope reduction or closure against updated business justification.

Incorrect Answers

A:

Set reporting frequency in the stage plan and monitor compliance. It can prevent stage highlight report omitted, but it does not control the stated recurrence risk: The board has been alerted to a problem without decision-supporting analysis.

B:

Require an initial business justification at project entry. It can prevent outline business case has no outcome, but it does not control the stated recurrence risk: The board has been alerted to a problem without decision-supporting analysis.

D:

Enforce procurement approval gates aligned with board authorization. It can prevent project manager self-authorizes project, but it does not control the stated recurrence risk: The board has been alerted to a problem without decision-supporting analysis.

Question 1152

Before changing its management arrangements, the project team observes: The manager warns of a forthcoming cost exception at the boundary but provides no alternative responses or assessment of continuing value. What is the most useful first check?

  1. Check the planned highlight frequency versus actual reports
  2. Ask what organizational outcome the proposed application should enable
  3. Check whether the exception report includes feasible corrective alternatives
  4. Inspect the latest board minutes for authorization of the project

Explanation

Correct Answer

C:

Check whether the exception report includes feasible corrective alternatives. The board has been alerted to a problem without decision-supporting analysis. The resulting action would be: Develop realistic exception options and recommendations for the project board.

Incorrect Answers

A:

Check the planned highlight frequency versus actual reports. That investigation addresses stage highlight report omitted; for the stated decision, check whether the exception report includes feasible corrective alternatives.

B:

Ask what organizational outcome the proposed application should enable. That investigation addresses outline business case has no outcome; for the stated decision, check whether the exception report includes feasible corrective alternatives.

D:

Inspect the latest board minutes for authorization of the project. That investigation addresses project manager self-authorizes project; for the stated decision, check whether the exception report includes feasible corrective alternatives.

Question 1153

A project manager encounters this situation: A project board withdraws funding and tells the manager to delete all project files immediately, although obligations and partly completed products remain. Which action most appropriately applies PRINCE2 7?

  1. Share emerging lessons and potential improvements through checkpoints while delivery is underway
  2. Treat startup approval as authorization for initiation only and seek separate project authorization later
  3. Require evidence of acceptance and outstanding action disposition before authorizing closure
  4. Execute controlled premature closure, account for outstanding commitments and hand over relevant products or actions

Explanation

Correct Answer

D:

Execute controlled premature closure, account for outstanding commitments and hand over relevant products or actions. Termination was mistaken for permission to abandon governance and records. Closing a project is a controlled process even when the project ends early.

Incorrect Answers

A:

Share emerging lessons and potential improvements through checkpoints while delivery is underway. It applies to team records lessons too late; the current decision depends on this finding: Termination was mistaken for permission to abandon governance and records.

B:

Treat startup approval as authorization for initiation only and seek separate project authorization later. It applies to premature authorization of whole project; the current decision depends on this finding: Termination was mistaken for permission to abandon governance and records.

C:

Require evidence of acceptance and outstanding action disposition before authorizing closure. It applies to closure decision without user evidence; the current decision depends on this finding: Termination was mistaken for permission to abandon governance and records.

Question 1154

An assurance reviewer investigates: A project board withdraws funding and tells the manager to delete all project files immediately, although obligations and partly completed products remain. Which root cause is most consistent with the evidence?

  1. Initiation authorization is being confused with full delivery investment approval
  2. Team experience is not influencing current project controls
  3. Termination was mistaken for permission to abandon governance and records
  4. A board decision would terminate governance without validating completion and handover

Explanation

Correct Answer

C:

Termination was mistaken for permission to abandon governance and records. That cause fits the described evidence. The relevant governance rule is: Closing a project is a controlled process even when the project ends early. The appropriate response would be to execute controlled premature closure, account for outstanding commitments and hand over relevant products or actions.

Incorrect Answers

A:

Initiation authorization is being confused with full delivery investment approval. This could explain a different issue concerning premature authorization of whole project, but the reported conditions instead indicate: Termination was mistaken for permission to abandon governance and records.

B:

Team experience is not influencing current project controls. This could explain a different issue concerning team records lessons too late, but the reported conditions instead indicate: Termination was mistaken for permission to abandon governance and records.

D:

A board decision would terminate governance without validating completion and handover. This could explain a different issue concerning closure decision without user evidence, but the reported conditions instead indicate: Termination was mistaken for permission to abandon governance and records.

Question 1155

A product or management action is said to resolve: A project board withdraws funding and tells the manager to delete all project files immediately, although obligations and partly completed products remain. Which verification is strongest?

  1. Closure records cover remaining risks, contracts, records and authorized follow-on actions
  2. The board separately considers initiation outputs before releasing major delivery commitment
  3. The board's closure decision is supported by acceptance and follow-on evidence
  4. The project manager can adapt later work based on timely documented lessons

Explanation

Correct Answer

A:

Closure records cover remaining risks, contracts, records and authorized follow-on actions. This is the observable outcome expected after the action: Execute controlled premature closure, account for outstanding commitments and hand over relevant products or actions. It tests the weakness that termination was mistaken for permission to abandon governance and records.

Incorrect Answers

B:

The board separately considers initiation outputs before releasing major delivery commitment. That would verify premature authorization of whole project, not the outcome at issue. The evidence needed for this situation is: Closure records cover remaining risks, contracts, records and authorized follow-on actions.

C:

The board's closure decision is supported by acceptance and follow-on evidence. That would verify closure decision without user evidence, not the outcome at issue. The evidence needed for this situation is: Closure records cover remaining risks, contracts, records and authorized follow-on actions.

D:

The project manager can adapt later work based on timely documented lessons. That would verify team records lessons too late, not the outcome at issue. The evidence needed for this situation is: Closure records cover remaining risks, contracts, records and authorized follow-on actions.

Question 1156

A board wants to understand the governance reasoning behind addressing: A project board withdraws funding and tells the manager to delete all project files immediately, although obligations and partly completed products remain. Which principle best fits?

  1. Starting up and initiating establish progressively stronger authorization evidence
  2. Directing a project includes authorization to close on a defensible completion basis
  3. Closing a project is a controlled process even when the project ends early
  4. Managing product delivery contributes progress and learning information to the project manager

Explanation

Correct Answer

C:

Closing a project is a controlled process even when the project ends early. This principle matters here because termination was mistaken for permission to abandon governance and records. The response should tackle the stated project-control deficiency.

Incorrect Answers

A:

Starting up and initiating establish progressively stronger authorization evidence. That principle is more directly associated with premature authorization of whole project. The present case concerns the weakness that termination was mistaken for permission to abandon governance and records.

B:

Directing a project includes authorization to close on a defensible completion basis. That principle is more directly associated with closure decision without user evidence. The present case concerns the weakness that termination was mistaken for permission to abandon governance and records.

D:

Managing product delivery contributes progress and learning information to the project manager. That principle is more directly associated with team records lessons too late. The present case concerns the weakness that termination was mistaken for permission to abandon governance and records.

Question 1157

The project board asks for a sustainable improvement after: A project board withdraws funding and tells the manager to delete all project files immediately, although obligations and partly completed products remain. Which guardrail should be established?

  1. Include lesson observations in agreed checkpoint content
  2. Use distinct initiation and project authorization decision records
  3. Maintain a premature-closure checklist for contracts and unfinished outputs
  4. Include senior-user acceptance in closure authorization conditions

Explanation

Correct Answer

C:

Maintain a premature-closure checklist for contracts and unfinished outputs. That preventive control addresses a repeated failure in which termination was mistaken for permission to abandon governance and records. Effectiveness can be checked by: Closure records cover remaining risks, contracts, records and authorized follow-on actions.

Incorrect Answers

A:

Include lesson observations in agreed checkpoint content. It can prevent team records lessons too late, but it does not control the stated recurrence risk: Termination was mistaken for permission to abandon governance and records.

B:

Use distinct initiation and project authorization decision records. It can prevent premature authorization of whole project, but it does not control the stated recurrence risk: Termination was mistaken for permission to abandon governance and records.

D:

Include senior-user acceptance in closure authorization conditions. It can prevent closure decision without user evidence, but it does not control the stated recurrence risk: Termination was mistaken for permission to abandon governance and records.

Question 1158

For this project problem—A project board withdraws funding and tells the manager to delete all project files immediately, although obligations and partly completed products remain—which initial review would most directly focus the response?

  1. Examine what funding and scope the board actually authorized
  2. Inspect the user acceptance and open quality findings
  3. Inventory unresolved agreements, deliveries and operational obligations
  4. Review the bottleneck incidents and their dates against checkpoint communications

Explanation

Correct Answer

C:

Inventory unresolved agreements, deliveries and operational obligations. Termination was mistaken for permission to abandon governance and records. The resulting action would be: Execute controlled premature closure, account for outstanding commitments and hand over relevant products or actions.

Incorrect Answers

A:

Examine what funding and scope the board actually authorized. That investigation addresses premature authorization of whole project; for the stated decision, examine inventory unresolved agreements, deliveries and operational obligations.

B:

Inspect the user acceptance and open quality findings. That investigation addresses closure decision without user evidence; for the stated decision, examine inventory unresolved agreements, deliveries and operational obligations.

D:

Review the bottleneck incidents and their dates against checkpoint communications. That investigation addresses team records lessons too late; for the stated decision, examine inventory unresolved agreements, deliveries and operational obligations.

Question 1159

Which response should the responsible project role take for this situation: A new mobile service meets its tests but no department has accepted responsibility for support after the project closes?

  1. Correct the checkpoint report and resolve or escalate the quality failure before declaring completion
  2. Complete the benefits management approach with accountable post-project ownership and measurements
  3. Confirm product acceptance and transfer support responsibility to named operational owners
  4. Require evidence of acceptance and outstanding action disposition before authorizing closure

Explanation

Correct Answer

C:

Confirm product acceptance and transfer support responsibility to named operational owners. Handover arrangements are incomplete despite technical product readiness. Controlled closure ensures products can be used and sustained after project teams disband.

Incorrect Answers

A:

Correct the checkpoint report and resolve or escalate the quality failure before declaring completion. It applies to checkpoint claims complete despite failed test; the current decision depends on this finding: Handover arrangements are incomplete despite technical product readiness.

B:

Complete the benefits management approach with accountable post-project ownership and measurements. It applies to benefit realization ownership not transferred; the current decision depends on this finding: Handover arrangements are incomplete despite technical product readiness.

D:

Require evidence of acceptance and outstanding action disposition before authorizing closure. It applies to closure decision without user evidence; the current decision depends on this finding: Handover arrangements are incomplete despite technical product readiness.

Question 1160

The project has the following difficulty: A new mobile service meets its tests but no department has accepted responsibility for support after the project closes. What underlying management failure best explains it?

  1. Outcome accountability has not been set during initiation
  2. Handover arrangements are incomplete despite technical product readiness
  3. Team progress reporting is based on activity rather than accepted product evidence
  4. A board decision would terminate governance without validating completion and handover

Explanation

Correct Answer

B:

Handover arrangements are incomplete despite technical product readiness. That cause fits the described evidence. The relevant governance rule is: Controlled closure ensures products can be used and sustained after project teams disband. The appropriate response would be to confirm product acceptance and transfer support responsibility to named operational owners.

Incorrect Answers

A:

Outcome accountability has not been set during initiation. This could explain a different issue concerning benefit realization ownership not transferred, but the reported conditions instead indicate: Handover arrangements are incomplete despite technical product readiness.

C:

Team progress reporting is based on activity rather than accepted product evidence. This could explain a different issue concerning checkpoint claims complete despite failed test, but the reported conditions instead indicate: Handover arrangements are incomplete despite technical product readiness.

D:

A board decision would terminate governance without validating completion and handover. This could explain a different issue concerning closure decision without user evidence, but the reported conditions instead indicate: Handover arrangements are incomplete despite technical product readiness.


PRINCE2 7 Practitioner Practice Tests

Purchase Individually

PRINCE2 7 Practitioner Premium File

Premium File
PRINCE2 7 Practitioner Premium File
93 Q&A
$76.99$69.99

Site Search:

 

VISA, MasterCard, AmericanExpress, UnionPay

SPECIAL OFFER: GET 10% OFF

ExamCollection Premium

ExamCollection Premium Files

Pass your Exam with ExamCollection's PREMIUM files!

  • ExamCollection Certified Safe Files
  • Guaranteed to have ACTUAL Exam Questions
  • Up-to-Date Exam Study Material - Verified by Experts
  • Instant Downloads
Enter Your Email Address to Receive Your 10% Off Discount Code
A Confirmation Link will be sent to this email address to verify your login
We value your privacy. We will not rent or sell your email address

SPECIAL OFFER: GET 10% OFF

Use Discount Code:

MIN10OFF

A confirmation link was sent to your e-mail.
Please check your mailbox for a message from support@examcollection.com and follow the directions.

Next

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.