Question 1180
During application of PRINCE2 7, what governing idea is illustrated by: Five low-severity issues remain unresolved at project acceptance, but the team removes them from the log to close quickly?
- Team managers deliver agreed products rather than set unapproved project requirements
- Stage boundaries are opportunities to learn before the next investment decision
- Closure can transfer accepted residual actions rather than pretend none exist
- Directing a project includes authorization to close on a defensible completion basis
Explanation
Correct Answer
C:Closure can transfer accepted residual actions rather than pretend none exist. This principle matters here because project closure is being achieved by hiding residual obligations. The response should tackle the stated project-control deficiency.
Incorrect Answers
A:Team managers deliver agreed products rather than set unapproved project requirements. That principle is more directly associated with team manager changes acceptance criteria. The present case concerns the weakness that project closure is being achieved by hiding residual obligations.
B:Stage boundaries are opportunities to learn before the next investment decision. That principle is more directly associated with stage report omits lessons. The present case concerns the weakness that project closure is being achieved by hiding residual obligations.
D:Directing a project includes authorization to close on a defensible completion basis. That principle is more directly associated with closure decision without user evidence. The present case concerns the weakness that project closure is being achieved by hiding residual obligations.
Question 1181
The project resolved this issue: Five low-severity issues remain unresolved at project acceptance, but the team removes them from the log to close quickly. Which enduring preventive control would most directly reduce recurrence?
- Audit issue disposition before board closure approval
- Reconfirm acceptance criteria with each work package
- Include senior-user acceptance in closure authorization conditions
- Require lessons-log review in boundary planning
Explanation
Correct Answer
A:Audit issue disposition before board closure approval. That preventive control addresses a repeated failure in which project closure is being achieved by hiding residual obligations. Effectiveness can be checked by: Each remaining issue has an accepted owner and planned resolution after closure.
Incorrect Answers
B:Reconfirm acceptance criteria with each work package. It can prevent team manager changes acceptance criteria, but it does not control the stated recurrence risk: Project closure is being achieved by hiding residual obligations.
C:Include senior-user acceptance in closure authorization conditions. It can prevent closure decision without user evidence, but it does not control the stated recurrence risk: Project closure is being achieved by hiding residual obligations.
D:Require lessons-log review in boundary planning. It can prevent stage report omits lessons, but it does not control the stated recurrence risk: Project closure is being achieved by hiding residual obligations.
Question 1182
An assurance reviewer begins examining: Five low-severity issues remain unresolved at project acceptance, but the team removes them from the log to close quickly. Which evidence should they inspect first?
- Compare the team test plan with approved product descriptions
- Examine lessons captured from supplier procurement and handover
- Check which registered issues are still open and who will own them
- Inspect the user acceptance and open quality findings
Explanation
Correct Answer
C:Check which registered issues are still open and who will own them. Project closure is being achieved by hiding residual obligations. The resulting action would be: Agree and assign follow-on action ownership and include it in closure documentation.
Incorrect Answers
A:Compare the team test plan with approved product descriptions. That investigation addresses team manager changes acceptance criteria; for the stated decision, check which registered issues are still open and who will own them.
B:Examine lessons captured from supplier procurement and handover. That investigation addresses stage report omits lessons; for the stated decision, check which registered issues are still open and who will own them.
D:Inspect the user acceptance and open quality findings. That investigation addresses closure decision without user evidence; for the stated decision, check which registered issues are still open and who will own them.
Question 1183
During a project review, the team reports: A healthcare project closes after installing appointment tools, although patient waiting-time benefits will only become measurable next quarter. What is the best authorized corrective action?
- Notify the project manager promptly of the work package forecast exception
- Replan the stage using the actual resource constraint and present credible forecasts
- Confirm post-project benefits review ownership and timing with the operational business
- Raise the proposed change through the agreed issue/work package route instead of altering the target alone
Explanation
Correct Answer
C:Confirm post-project benefits review ownership and timing with the operational business. Outcome measurement is at risk of being abandoned when the delivery team leaves. Closure should preserve post-project benefits management arrangements.
Incorrect Answers
A:Notify the project manager promptly of the work package forecast exception. It applies to team forecast breaches work package tolerance; the current decision depends on this finding: Outcome measurement is at risk of being abandoned when the delivery team leaves.
B:Replan the stage using the actual resource constraint and present credible forecasts. It applies to next stage forecast ignores supplier capacity; the current decision depends on this finding: Outcome measurement is at risk of being abandoned when the delivery team leaves.
D:Raise the proposed change through the agreed issue/work package route instead of altering the target alone. It applies to team manager changes acceptance criteria; the current decision depends on this finding: Outcome measurement is at risk of being abandoned when the delivery team leaves.
Question 1184
The project manager wants to understand why this occurred: A healthcare project closes after installing appointment tools, although patient waiting-time benefits will only become measurable next quarter. What is the best diagnosis?
- Outcome measurement is at risk of being abandoned when the delivery team leaves
- Delegated team tolerance has been breached without timely escalation
- The next stage plan contains an infeasible delivery-capacity assumption
- Delivery discretion is being used to change baselined requirements
Explanation
Correct Answer
A:Outcome measurement is at risk of being abandoned when the delivery team leaves. That cause fits the described evidence. The relevant governance rule is: Closure should preserve post-project benefits management arrangements. The appropriate response would be to confirm post-project benefits review ownership and timing with the operational business.
Incorrect Answers
B:Delegated team tolerance has been breached without timely escalation. This could explain a different issue concerning team forecast breaches work package tolerance, but the reported conditions instead indicate: Outcome measurement is at risk of being abandoned when the delivery team leaves.
C:The next stage plan contains an infeasible delivery-capacity assumption. This could explain a different issue concerning next stage forecast ignores supplier capacity, but the reported conditions instead indicate: Outcome measurement is at risk of being abandoned when the delivery team leaves.
D:Delivery discretion is being used to change baselined requirements. This could explain a different issue concerning team manager changes acceptance criteria, but the reported conditions instead indicate: Outcome measurement is at risk of being abandoned when the delivery team leaves.
Question 1185
What evidence would most credibly confirm effective management of this situation: A healthcare project closes after installing appointment tools, although patient waiting-time benefits will only become measurable next quarter?
- A named owner accepts a review date and baseline measures for waiting times
- The board authorizes a schedule consistent with supplier capacity and tolerances
- The project manager is informed early enough to choose appropriate control action
- The final product meets the approved criterion or has a properly authorized change
Explanation
Correct Answer
A:A named owner accepts a review date and baseline measures for waiting times. This is the observable outcome expected after the action: Confirm post-project benefits review ownership and timing with the operational business. It tests the weakness that outcome measurement is at risk of being abandoned when the delivery team leaves.
Incorrect Answers
B:The board authorizes a schedule consistent with supplier capacity and tolerances. That would verify next stage forecast ignores supplier capacity, not the outcome at issue. The evidence needed for this situation is: A named owner accepts a review date and baseline measures for waiting times.
C:The project manager is informed early enough to choose appropriate control action. That would verify team forecast breaches work package tolerance, not the outcome at issue. The evidence needed for this situation is: A named owner accepts a review date and baseline measures for waiting times.
D:The final product meets the approved criterion or has a properly authorized change. That would verify team manager changes acceptance criteria, not the outcome at issue. The evidence needed for this situation is: A named owner accepts a review date and baseline measures for waiting times.
Question 1186
Which general PRINCE2 control concept is most pertinent to this problem: A healthcare project closes after installing appointment tools, although patient waiting-time benefits will only become measurable next quarter?
- Boundary planning uses current evidence to produce realistic next-stage commitments
- Closure should preserve post-project benefits management arrangements
- A team manager must raise forecast work-package exceptions at the correct level
- Team managers deliver agreed products rather than set unapproved project requirements
Explanation
Correct Answer
B:Closure should preserve post-project benefits management arrangements. This principle matters here because outcome measurement is at risk of being abandoned when the delivery team leaves. The response should tackle the stated project-control deficiency.
Incorrect Answers
A:Boundary planning uses current evidence to produce realistic next-stage commitments. That principle is more directly associated with next stage forecast ignores supplier capacity. The present case concerns the weakness that outcome measurement is at risk of being abandoned when the delivery team leaves.
C:A team manager must raise forecast work-package exceptions at the correct level. That principle is more directly associated with team forecast breaches work package tolerance. The present case concerns the weakness that outcome measurement is at risk of being abandoned when the delivery team leaves.
D:Team managers deliver agreed products rather than set unapproved project requirements. That principle is more directly associated with team manager changes acceptance criteria. The present case concerns the weakness that outcome measurement is at risk of being abandoned when the delivery team leaves.
Question 1187
After an effective correction, which management improvement best prevents a repeat of: A healthcare project closes after installing appointment tools, although patient waiting-time benefits will only become measurable next quarter?
- Reconfirm acceptance criteria with each work package
- Include benefits handover in end project approval materials
- Monitor forecast-to-tolerance continuously for critical packages
- Verify critical supplier capacity before stage plans are submitted
Explanation
Correct Answer
B:Include benefits handover in end project approval materials. That preventive control addresses a repeated failure in which outcome measurement is at risk of being abandoned when the delivery team leaves. Effectiveness can be checked by: A named owner accepts a review date and baseline measures for waiting times.
Incorrect Answers
A:Reconfirm acceptance criteria with each work package. It can prevent team manager changes acceptance criteria, but it does not control the stated recurrence risk: Outcome measurement is at risk of being abandoned when the delivery team leaves.
C:Monitor forecast-to-tolerance continuously for critical packages. It can prevent team forecast breaches work package tolerance, but it does not control the stated recurrence risk: Outcome measurement is at risk of being abandoned when the delivery team leaves.
D:Verify critical supplier capacity before stage plans are submitted. It can prevent next stage forecast ignores supplier capacity, but it does not control the stated recurrence risk: Outcome measurement is at risk of being abandoned when the delivery team leaves.
Question 1188
Before changing its management arrangements, the project team observes: A healthcare project closes after installing appointment tools, although patient waiting-time benefits will only become measurable next quarter. What is the most useful first check?
- Read the benefits management approach for the review schedule and responsible owner
- Read the supplier's crew availability against the proposed parallel schedule
- Compare the team test plan with approved product descriptions
- Compare team delivery estimates with authorized work package tolerance
Explanation
Correct Answer
A:Read the benefits management approach for the review schedule and responsible owner. Outcome measurement is at risk of being abandoned when the delivery team leaves. The resulting action would be: Confirm post-project benefits review ownership and timing with the operational business.
Incorrect Answers
B:Read the supplier's crew availability against the proposed parallel schedule. That investigation addresses next stage forecast ignores supplier capacity; for the stated decision, examine read the benefits management approach for the review schedule and responsible owner.
C:Compare the team test plan with approved product descriptions. That investigation addresses team manager changes acceptance criteria; for the stated decision, examine read the benefits management approach for the review schedule and responsible owner.
D:Compare team delivery estimates with authorized work package tolerance. That investigation addresses team forecast breaches work package tolerance; for the stated decision, examine read the benefits management approach for the review schedule and responsible owner.
Question 1189
A project manager encounters this situation: An infrastructure supplier says delivery is complete but the customer has not accepted the final project product description. Which action most appropriately applies PRINCE2 7?
- Correct the checkpoint report and resolve or escalate the quality failure before declaring completion
- Obtain appropriate customer acceptance or authorized disposition of exceptions before routine closure
- Review the work package's completed products and quality results before confirming completion
- Require evidence of acceptance and outstanding action disposition before authorizing closure
Explanation
Correct Answer
B:Obtain appropriate customer acceptance or authorized disposition of exceptions before routine closure. Supplier completion claims do not substitute for required customer acceptance. Closure should verify that the project's products have been accepted as planned.
Incorrect Answers
A:Correct the checkpoint report and resolve or escalate the quality failure before declaring completion. It applies to checkpoint claims complete despite failed test; the current decision depends on this finding: Supplier completion claims do not substitute for required customer acceptance.
C:Review the work package's completed products and quality results before confirming completion. It applies to completed product not checked; the current decision depends on this finding: Supplier completion claims do not substitute for required customer acceptance.
D:Require evidence of acceptance and outstanding action disposition before authorizing closure. It applies to closure decision without user evidence; the current decision depends on this finding: Supplier completion claims do not substitute for required customer acceptance.
Question 1190
An assurance reviewer investigates: An infrastructure supplier says delivery is complete but the customer has not accepted the final project product description. Which root cause is most consistent with the evidence?
- Supplier completion claims do not substitute for required customer acceptance
- Delivery declarations are accepted without product-based control evidence
- Team progress reporting is based on activity rather than accepted product evidence
- A board decision would terminate governance without validating completion and handover
Explanation
Correct Answer
A:Supplier completion claims do not substitute for required customer acceptance. That cause fits the described evidence. The relevant governance rule is: Closure should verify that the project's products have been accepted as planned. The appropriate response would be to obtain appropriate customer acceptance or authorized disposition of exceptions before routine closure.
Incorrect Answers
B:Delivery declarations are accepted without product-based control evidence. This could explain a different issue concerning completed product not checked, but the reported conditions instead indicate: Supplier completion claims do not substitute for required customer acceptance.
C:Team progress reporting is based on activity rather than accepted product evidence. This could explain a different issue concerning checkpoint claims complete despite failed test, but the reported conditions instead indicate: Supplier completion claims do not substitute for required customer acceptance.
D:A board decision would terminate governance without validating completion and handover. This could explain a different issue concerning closure decision without user evidence, but the reported conditions instead indicate: Supplier completion claims do not substitute for required customer acceptance.