Question 1190
An assurance reviewer investigates: An infrastructure supplier says delivery is complete but the customer has not accepted the final project product description. Which root cause is most consistent with the evidence?
Explanation
Correct Answer
Supplier completion claims do not substitute for required customer acceptance. That cause fits the described evidence. The relevant governance rule is: Closure should verify that the project's products have been accepted as planned. The appropriate response would be to obtain appropriate customer acceptance or authorized disposition of exceptions before routine closure.
Incorrect Answers
Delivery declarations are accepted without product-based control evidence. This could explain a different issue concerning completed product not checked, but the reported conditions instead indicate: Supplier completion claims do not substitute for required customer acceptance.
Team progress reporting is based on activity rather than accepted product evidence. This could explain a different issue concerning checkpoint claims complete despite failed test, but the reported conditions instead indicate: Supplier completion claims do not substitute for required customer acceptance.
A board decision would terminate governance without validating completion and handover. This could explain a different issue concerning closure decision without user evidence, but the reported conditions instead indicate: Supplier completion claims do not substitute for required customer acceptance.



PRINCE2 7 Practitioner Practice Tests