Pass Your PRINCE2 PRINCE2 7 Practitioner Exam Easy!

PRINCE2 PRINCE2 7 Practitioner Exam Questions & Answers, Accurate & Verified By IT Experts

Instant Download, Free Fast Updates, 99.6% Pass Rate

PRINCE2 7 Practitioner Premium VCE File

PRINCE2 PRINCE2 7 Practitioner Premium File

93 Questions & Answers

Last Update: Nov 02, 2026

$69.99

PRINCE2 7 Practitioner Bundle gives you unlimited access to "PRINCE2 7 Practitioner" files. However, this does not replace the need for a .vce exam simulator. To download VCE exam simulator click here
PRINCE2 7 Practitioner Premium VCE File
PRINCE2 PRINCE2 7 Practitioner Premium File

93 Questions & Answers

Last Update: Nov 02, 2026

$69.99

PRINCE2 PRINCE2 7 Practitioner Exam Bundle gives you unlimited access to "PRINCE2 7 Practitioner" files. However, this does not replace the need for a .vce exam simulator. To download your .vce exam simulator click here

PRINCE2 PRINCE2 7 Practitioner Practice Test 120

Question 1190

An assurance reviewer investigates: An infrastructure supplier says delivery is complete but the customer has not accepted the final project product description. Which root cause is most consistent with the evidence?

  1. Supplier completion claims do not substitute for required customer acceptance
  2. Delivery declarations are accepted without product-based control evidence
  3. Team progress reporting is based on activity rather than accepted product evidence
  4. A board decision would terminate governance without validating completion and handover

Explanation

Correct Answer

A:

Supplier completion claims do not substitute for required customer acceptance. That cause fits the described evidence. The relevant governance rule is: Closure should verify that the project's products have been accepted as planned. The appropriate response would be to obtain appropriate customer acceptance or authorized disposition of exceptions before routine closure.

Incorrect Answers

B:

Delivery declarations are accepted without product-based control evidence. This could explain a different issue concerning completed product not checked, but the reported conditions instead indicate: Supplier completion claims do not substitute for required customer acceptance.

C:

Team progress reporting is based on activity rather than accepted product evidence. This could explain a different issue concerning checkpoint claims complete despite failed test, but the reported conditions instead indicate: Supplier completion claims do not substitute for required customer acceptance.

D:

A board decision would terminate governance without validating completion and handover. This could explain a different issue concerning closure decision without user evidence, but the reported conditions instead indicate: Supplier completion claims do not substitute for required customer acceptance.

Question 1191

A product or management action is said to resolve: An infrastructure supplier says delivery is complete but the customer has not accepted the final project product description. Which verification is strongest?

  1. The board's closure decision is supported by acceptance and follow-on evidence
  2. Signed acceptance evidence covers all mandatory product criteria or approved deviations
  3. Reported completion matches successful quality checks and remaining work
  4. Product completion is supported by agreed quality and acceptance records

Explanation

Correct Answer

B:

Signed acceptance evidence covers all mandatory product criteria or approved deviations. This is the observable outcome expected after the action: Obtain appropriate customer acceptance or authorized disposition of exceptions before routine closure. It tests the weakness that supplier completion claims do not substitute for required customer acceptance.

Incorrect Answers

A:

The board's closure decision is supported by acceptance and follow-on evidence. That would verify closure decision without user evidence, not the outcome at issue. The evidence needed for this situation is: Signed acceptance evidence covers all mandatory product criteria or approved deviations.

C:

Reported completion matches successful quality checks and remaining work. That would verify checkpoint claims complete despite failed test, not the outcome at issue. The evidence needed for this situation is: Signed acceptance evidence covers all mandatory product criteria or approved deviations.

D:

Product completion is supported by agreed quality and acceptance records. That would verify completed product not checked, not the outcome at issue. The evidence needed for this situation is: Signed acceptance evidence covers all mandatory product criteria or approved deviations.

Question 1192

A board wants to understand the governance reasoning behind addressing: An infrastructure supplier says delivery is complete but the customer has not accepted the final project product description. Which principle best fits?

  1. Closure should verify that the project's products have been accepted as planned
  2. Team-level control includes delivering products that satisfy their acceptance specifications
  3. Directing a project includes authorization to close on a defensible completion basis
  4. Stage control monitors work package results against authorized product descriptions

Explanation

Correct Answer

A:

Closure should verify that the project's products have been accepted as planned. This principle matters here because supplier completion claims do not substitute for required customer acceptance. The response should tackle the stated project-control deficiency.

Incorrect Answers

B:

Team-level control includes delivering products that satisfy their acceptance specifications. That principle is more directly associated with checkpoint claims complete despite failed test. The present case concerns the weakness that supplier completion claims do not substitute for required customer acceptance.

C:

Directing a project includes authorization to close on a defensible completion basis. That principle is more directly associated with closure decision without user evidence. The present case concerns the weakness that supplier completion claims do not substitute for required customer acceptance.

D:

Stage control monitors work package results against authorized product descriptions. That principle is more directly associated with completed product not checked. The present case concerns the weakness that supplier completion claims do not substitute for required customer acceptance.

Question 1193

The project board asks for a sustainable improvement after: An infrastructure supplier says delivery is complete but the customer has not accepted the final project product description. Which guardrail should be established?

  1. Require acceptance records in the closure checklist
  2. Include senior-user acceptance in closure authorization conditions
  3. Require product evidence before closing delegated work
  4. Tie checkpoint status to quality records

Explanation

Correct Answer

A:

Require acceptance records in the closure checklist. That preventive control addresses a repeated failure in which supplier completion claims do not substitute for required customer acceptance. Effectiveness can be checked by: Signed acceptance evidence covers all mandatory product criteria or approved deviations.

Incorrect Answers

B:

Include senior-user acceptance in closure authorization conditions. It can prevent closure decision without user evidence, but it does not control the stated recurrence risk: Supplier completion claims do not substitute for required customer acceptance.

C:

Require product evidence before closing delegated work. It can prevent completed product not checked, but it does not control the stated recurrence risk: Supplier completion claims do not substitute for required customer acceptance.

D:

Tie checkpoint status to quality records. It can prevent checkpoint claims complete despite failed test, but it does not control the stated recurrence risk: Supplier completion claims do not substitute for required customer acceptance.

Question 1194

For this project problem—An infrastructure supplier says delivery is complete but the customer has not accepted the final project product description—which initial review would most directly focus the response?

  1. Examine the relevant quality register entry and product description
  2. Inspect the failed quality result against claimed progress
  3. Inspect the user acceptance and open quality findings
  4. Compare the customer acceptance criteria with recorded test and sign-off evidence

Explanation

Correct Answer

D:

Compare the customer acceptance criteria with recorded test and sign-off evidence. Supplier completion claims do not substitute for required customer acceptance. The resulting action would be: Obtain appropriate customer acceptance or authorized disposition of exceptions before routine closure.

Incorrect Answers

A:

Examine the relevant quality register entry and product description. That investigation addresses completed product not checked; for the stated decision, compare the customer acceptance criteria with recorded test and sign-off evidence.

B:

Inspect the failed quality result against claimed progress. That investigation addresses checkpoint claims complete despite failed test; for the stated decision, compare the customer acceptance criteria with recorded test and sign-off evidence.

C:

Inspect the user acceptance and open quality findings. That investigation addresses closure decision without user evidence; for the stated decision, compare the customer acceptance criteria with recorded test and sign-off evidence.

Question 1195

Which response should the responsible project role take for this situation: A building retrofit project finishes construction but never measures the emissions-reduction criteria that formed part of its approved business case?

  1. Develop an outline business case and align it with the project brief before seeking approval to initiate
  2. Require updated justification and next-stage forecasts before authorizing the stage
  3. Update the business case and provide revised forecasts to the board
  4. Record available sustainability performance and assign any later verification to a responsible operational owner

Explanation

Correct Answer

D:

Record available sustainability performance and assign any later verification to a responsible operational owner. Closing work focuses on construction rather than approved sustainability outcomes. Successful closure preserves accountability for approved project outcomes beyond delivery.

Incorrect Answers

A:

Develop an outline business case and align it with the project brief before seeking approval to initiate. It applies to outline business case has no outcome; the current decision depends on this finding: Closing work focuses on construction rather than approved sustainability outcomes.

B:

Require updated justification and next-stage forecasts before authorizing the stage. It applies to board authorizes stage without updated case; the current decision depends on this finding: Closing work focuses on construction rather than approved sustainability outcomes.

C:

Update the business case and provide revised forecasts to the board. It applies to business case not refreshed at boundary; the current decision depends on this finding: Closing work focuses on construction rather than approved sustainability outcomes.

Question 1196

The project has the following difficulty: A building retrofit project finishes construction but never measures the emissions-reduction criteria that formed part of its approved business case. What underlying management failure best explains it?

  1. Direction decisions are proceeding on stale investment evidence
  2. The proposed project is product-led without an initial rationale for its cost
  3. The stage decision would rely on assumptions superseded by experience
  4. Closing work focuses on construction rather than approved sustainability outcomes

Explanation

Correct Answer

D:

Closing work focuses on construction rather than approved sustainability outcomes. That cause fits the described evidence. The relevant governance rule is: Successful closure preserves accountability for approved project outcomes beyond delivery. The appropriate response would be to record available sustainability performance and assign any later verification to a responsible operational owner.

Incorrect Answers

A:

Direction decisions are proceeding on stale investment evidence. This could explain a different issue concerning board authorizes stage without updated case, but the reported conditions instead indicate: Closing work focuses on construction rather than approved sustainability outcomes.

B:

The proposed project is product-led without an initial rationale for its cost. This could explain a different issue concerning outline business case has no outcome, but the reported conditions instead indicate: Closing work focuses on construction rather than approved sustainability outcomes.

C:

The stage decision would rely on assumptions superseded by experience. This could explain a different issue concerning business case not refreshed at boundary, but the reported conditions instead indicate: Closing work focuses on construction rather than approved sustainability outcomes.

Question 1197

The project board requests closure evidence for this issue: A building retrofit project finishes construction but never measures the emissions-reduction criteria that formed part of its approved business case. Which observation best supports approval?

  1. Decision makers can state why the investment is justified at outline level
  2. Closure report and follow-on plan account for measured or scheduled sustainability results
  3. The next authorization reflects revised cost, benefit and risk evidence
  4. Stage authorization records a current business case and understood risk exposure

Explanation

Correct Answer

B:

Closure report and follow-on plan account for measured or scheduled sustainability results. This is the observable outcome expected after the action: Record available sustainability performance and assign any later verification to a responsible operational owner. It tests the weakness that closing work focuses on construction rather than approved sustainability outcomes.

Incorrect Answers

A:

Decision makers can state why the investment is justified at outline level. That would verify outline business case has no outcome, not the outcome at issue. The evidence needed for this situation is: Closure report and follow-on plan account for measured or scheduled sustainability results.

C:

The next authorization reflects revised cost, benefit and risk evidence. That would verify business case not refreshed at boundary, not the outcome at issue. The evidence needed for this situation is: Closure report and follow-on plan account for measured or scheduled sustainability results.

D:

Stage authorization records a current business case and understood risk exposure. That would verify board authorizes stage without updated case, not the outcome at issue. The evidence needed for this situation is: Closure report and follow-on plan account for measured or scheduled sustainability results.

Question 1198

For the project situation—A building retrofit project finishes construction but never measures the emissions-reduction criteria that formed part of its approved business case—which underlying method concept should guide the decision?

  1. Successful closure preserves accountability for approved project outcomes beyond delivery
  2. The project board directs investment based on continuing justification at stage boundaries
  3. Stage boundary planning reassesses continued business justification
  4. Starting up tests whether a project appears worthwhile before major resources are spent

Explanation

Correct Answer

A:

Successful closure preserves accountability for approved project outcomes beyond delivery. This principle matters here because closing work focuses on construction rather than approved sustainability outcomes. The response should tackle the stated project-control deficiency.

Incorrect Answers

B:

The project board directs investment based on continuing justification at stage boundaries. That principle is more directly associated with board authorizes stage without updated case. The present case concerns the weakness that closing work focuses on construction rather than approved sustainability outcomes.

C:

Stage boundary planning reassesses continued business justification. That principle is more directly associated with business case not refreshed at boundary. The present case concerns the weakness that closing work focuses on construction rather than approved sustainability outcomes.

D:

Starting up tests whether a project appears worthwhile before major resources are spent. That principle is more directly associated with outline business case has no outcome. The present case concerns the weakness that closing work focuses on construction rather than approved sustainability outcomes.

Question 1199

What ongoing assurance step best addresses the recurring risk seen here: A building retrofit project finishes construction but never measures the emissions-reduction criteria that formed part of its approved business case?

  1. Put current business case review on every stage authorization agenda
  2. Require an initial business justification at project entry
  3. Include sustainability measures in completion and benefits review planning
  4. Reconcile business case assumptions with closing stage performance

Explanation

Correct Answer

C:

Include sustainability measures in completion and benefits review planning. That preventive control addresses a repeated failure in which closing work focuses on construction rather than approved sustainability outcomes. Effectiveness can be checked by: Closure report and follow-on plan account for measured or scheduled sustainability results.

Incorrect Answers

A:

Put current business case review on every stage authorization agenda. It can prevent board authorizes stage without updated case, but it does not control the stated recurrence risk: Closing work focuses on construction rather than approved sustainability outcomes.

B:

Require an initial business justification at project entry. It can prevent outline business case has no outcome, but it does not control the stated recurrence risk: Closing work focuses on construction rather than approved sustainability outcomes.

D:

Reconcile business case assumptions with closing stage performance. It can prevent business case not refreshed at boundary, but it does not control the stated recurrence risk: Closing work focuses on construction rather than approved sustainability outcomes.

Question 1200

Before escalating a proposed solution, what should be checked about: A building retrofit project finishes construction but never measures the emissions-reduction criteria that formed part of its approved business case?

  1. Compare contamination cost estimates with the last board-approved forecast
  2. Ask what organizational outcome the proposed application should enable
  3. Compare new supplier estimates and benefit forecasts with the last baseline
  4. Compare approved emissions target against actual monitoring and scheduled future measurement

Explanation

Correct Answer

D:

Compare approved emissions target against actual monitoring and scheduled future measurement. Closing work focuses on construction rather than approved sustainability outcomes. The resulting action would be: Record available sustainability performance and assign any later verification to a responsible operational owner.

Incorrect Answers

A:

Compare contamination cost estimates with the last board-approved forecast. That investigation addresses board authorizes stage without updated case; for the stated decision, compare approved emissions target against actual monitoring and scheduled future measurement.

B:

Ask what organizational outcome the proposed application should enable. That investigation addresses outline business case has no outcome; for the stated decision, compare approved emissions target against actual monitoring and scheduled future measurement.

C:

Compare new supplier estimates and benefit forecasts with the last baseline. That investigation addresses business case not refreshed at boundary; for the stated decision, compare approved emissions target against actual monitoring and scheduled future measurement.


PRINCE2 7 Practitioner Practice Tests

Purchase Individually

PRINCE2 7 Practitioner Premium File

Premium File
PRINCE2 7 Practitioner Premium File
93 Q&A
$76.99$69.99

Site Search:

 

VISA, MasterCard, AmericanExpress, UnionPay

SPECIAL OFFER: GET 10% OFF

ExamCollection Premium

ExamCollection Premium Files

Pass your Exam with ExamCollection's PREMIUM files!

  • ExamCollection Certified Safe Files
  • Guaranteed to have ACTUAL Exam Questions
  • Up-to-Date Exam Study Material - Verified by Experts
  • Instant Downloads
Enter Your Email Address to Receive Your 10% Off Discount Code
A Confirmation Link will be sent to this email address to verify your login
We value your privacy. We will not rent or sell your email address

SPECIAL OFFER: GET 10% OFF

Use Discount Code:

MIN10OFF

A confirmation link was sent to your e-mail.
Please check your mailbox for a message from support@examcollection.com and follow the directions.

Next

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.