Question 1070
A stage review identifies: A supplier team forecasts that a component will take twice the authorized work-package time and waits for the project manager's next monthly meeting. Which weakness in control or decision-making is most likely?
Explanation
Correct Answer
Delegated team tolerance has been breached without timely escalation. That cause fits the described evidence. The relevant governance rule is: A team manager must raise forecast work-package exceptions at the correct level. The appropriate response would be to notify the project manager promptly of the work package forecast exception.
Incorrect Answers
Team evidence is not being incorporated into forecast-based stage control. This could explain a different issue concerning checkpoint shows forecast tolerance breach, but the reported conditions instead indicate: Delegated team tolerance has been breached without timely escalation.
Delivery activity has begun without delegated project-manager control. This could explain a different issue concerning unapproved team work starts, but the reported conditions instead indicate: Delegated team tolerance has been breached without timely escalation.
Delegated responsibilities no longer match agreed assignments. This could explain a different issue concerning work package changed without agreement, but the reported conditions instead indicate: Delegated team tolerance has been breached without timely escalation.