Question 1090
For the project situation—A contracted team proposes a milestone extension within its local task list that would invalidate the project manager's stage assumptions—which underlying method concept should guide the decision?
Explanation
Correct Answer
Team-level plans support stage delivery but cannot silently override stage authority. This principle matters here because team estimates are no longer aligned with delegated stage control. The response should tackle the stated project-control deficiency.
Incorrect Answers
Stage boundary planning reassesses continued business justification. That principle is more directly associated with business case not refreshed at boundary. The present case concerns the weakness that team estimates are no longer aligned with delegated stage control.
Starting up screens for a viable approach before spending heavily on initiation. That principle is more directly associated with project mandate contains impossible date. The present case concerns the weakness that team estimates are no longer aligned with delegated stage control.
Work package control depends on clear, current agreements. That principle is more directly associated with work package changed without agreement. The present case concerns the weakness that team estimates are no longer aligned with delegated stage control.