Question 1110
An assurance reviewer begins examining: A project has discovered a better solution with different costs and benefits, but the next-stage review still uses the original business case. Which evidence should they inspect first?
- Ask what organizational outcome the proposed application should enable
- Compare contamination cost estimates with the last board-approved forecast
- Compare new supplier estimates and benefit forecasts with the last baseline
- Identify the effect of the proposed extension on the stage critical path
Explanation
Correct Answer
C:Compare new supplier estimates and benefit forecasts with the last baseline. The stage decision would rely on assumptions superseded by experience. The resulting action would be: Update the business case and provide revised forecasts to the board.
Incorrect Answers
A:Ask what organizational outcome the proposed application should enable. That investigation addresses outline business case has no outcome; for the stated decision, compare new supplier estimates and benefit forecasts with the last baseline.
B:Compare contamination cost estimates with the last board-approved forecast. That investigation addresses board authorizes stage without updated case; for the stated decision, compare new supplier estimates and benefit forecasts with the last baseline.
D:Identify the effect of the proposed extension on the stage critical path. That investigation addresses team plan conflicts with main stage; for the stated decision, compare new supplier estimates and benefit forecasts with the last baseline.
Question 1111
During a project review, the team reports: At the boundary, the project manager describes only schedule and cost performance even though the team identified reusable procurement improvements. What is the best authorized corrective action?
- Agree an appropriate project approach before committing procurement specifications
- Summarize relevant lessons and actions with the stage-boundary report
- Review relevant previous lessons during starting up and reflect them in the project brief and initiation stage plan
- Update the risk response and take authorized protective action during the current stage
Explanation
Correct Answer
B:Summarize relevant lessons and actions with the stage-boundary report. Organizational learning is being separated from planned future stage work. Stage boundaries are opportunities to learn before the next investment decision.
Incorrect Answers
A:Agree an appropriate project approach before committing procurement specifications. It applies to supplier selection before approach defined; the current decision depends on this finding: Organizational learning is being separated from planned future stage work.
C:Review relevant previous lessons during starting up and reflect them in the project brief and initiation stage plan. It applies to early lessons from similar initiative; the current decision depends on this finding: Organizational learning is being separated from planned future stage work.
D:Update the risk response and take authorized protective action during the current stage. It applies to risk warning ignored until stage end; the current decision depends on this finding: Organizational learning is being separated from planned future stage work.
Question 1112
The project manager wants to understand why this occurred: At the boundary, the project manager describes only schedule and cost performance even though the team identified reusable procurement improvements. What is the best diagnosis?
- A solution path is being committed before options and delivery approach are evaluated
- Organizational learning is being separated from planned future stage work
- Reusable experience is being omitted from the first feasibility decisions
- Risk control is being treated as a periodic stage-boundary activity only
Explanation
Correct Answer
B:Organizational learning is being separated from planned future stage work. That cause fits the described evidence. The relevant governance rule is: Stage boundaries are opportunities to learn before the next investment decision. The appropriate response would be to summarize relevant lessons and actions with the stage-boundary report.
Incorrect Answers
A:A solution path is being committed before options and delivery approach are evaluated. This could explain a different issue concerning supplier selection before approach defined, but the reported conditions instead indicate: Organizational learning is being separated from planned future stage work.
C:Reusable experience is being omitted from the first feasibility decisions. This could explain a different issue concerning early lessons from similar initiative, but the reported conditions instead indicate: Organizational learning is being separated from planned future stage work.
D:Risk control is being treated as a periodic stage-boundary activity only. This could explain a different issue concerning risk warning ignored until stage end, but the reported conditions instead indicate: Organizational learning is being separated from planned future stage work.
Question 1113
What evidence would most credibly confirm effective management of this situation: At the boundary, the project manager describes only schedule and cost performance even though the team identified reusable procurement improvements?
- Current stage controls reflect a feasible response and updated exposure
- Early planning includes responses to documented historic adoption failures
- The project brief explains the selected approach and its implications for later initiation
- The next stage plan reflects documented lessons from the preceding stage
Explanation
Correct Answer
D:The next stage plan reflects documented lessons from the preceding stage. This is the observable outcome expected after the action: Summarize relevant lessons and actions with the stage-boundary report. It tests the weakness that organizational learning is being separated from planned future stage work.
Incorrect Answers
A:Current stage controls reflect a feasible response and updated exposure. That would verify risk warning ignored until stage end, not the outcome at issue. The evidence needed for this situation is: The next stage plan reflects documented lessons from the preceding stage.
B:Early planning includes responses to documented historic adoption failures. That would verify early lessons from similar initiative, not the outcome at issue. The evidence needed for this situation is: The next stage plan reflects documented lessons from the preceding stage.
C:The project brief explains the selected approach and its implications for later initiation. That would verify supplier selection before approach defined, not the outcome at issue. The evidence needed for this situation is: The next stage plan reflects documented lessons from the preceding stage.
Question 1114
Which general PRINCE2 control concept is most pertinent to this problem: At the boundary, the project manager describes only schedule and cost performance even though the team identified reusable procurement improvements?
- Starting up should use experience before substantial initiation effort is authorized
- Stage boundaries are opportunities to learn before the next investment decision
- Controlling a stage includes managing risks when information changes
- A project approach informs how outputs may be delivered and whether initiation is sensible
Explanation
Correct Answer
B:Stage boundaries are opportunities to learn before the next investment decision. This principle matters here because organizational learning is being separated from planned future stage work. The response should tackle the stated project-control deficiency.
Incorrect Answers
A:Starting up should use experience before substantial initiation effort is authorized. That principle is more directly associated with early lessons from similar initiative. The present case concerns the weakness that organizational learning is being separated from planned future stage work.
C:Controlling a stage includes managing risks when information changes. That principle is more directly associated with risk warning ignored until stage end. The present case concerns the weakness that organizational learning is being separated from planned future stage work.
D:A project approach informs how outputs may be delivered and whether initiation is sensible. That principle is more directly associated with supplier selection before approach defined. The present case concerns the weakness that organizational learning is being separated from planned future stage work.
Question 1115
After an effective correction, which management improvement best prevents a repeat of: At the boundary, the project manager describes only schedule and cost performance even though the team identified reusable procurement improvements?
- Include a lessons review in startup activities
- Require lessons-log review in boundary planning
- Review major risk indicators at checkpoint meetings
- Require a high-level options check before procurement
Explanation
Correct Answer
B:Require lessons-log review in boundary planning. That preventive control addresses a repeated failure in which organizational learning is being separated from planned future stage work. Effectiveness can be checked by: The next stage plan reflects documented lessons from the preceding stage.
Incorrect Answers
A:Include a lessons review in startup activities. It can prevent early lessons from similar initiative, but it does not control the stated recurrence risk: Organizational learning is being separated from planned future stage work.
C:Review major risk indicators at checkpoint meetings. It can prevent risk warning ignored until stage end, but it does not control the stated recurrence risk: Organizational learning is being separated from planned future stage work.
D:Require a high-level options check before procurement. It can prevent supplier selection before approach defined, but it does not control the stated recurrence risk: Organizational learning is being separated from planned future stage work.
Question 1116
Before changing its management arrangements, the project team observes: At the boundary, the project manager describes only schedule and cost performance even though the team identified reusable procurement improvements. What is the most useful first check?
- Verify the supplier license status and its effect on planned products
- Examine lessons captured from supplier procurement and handover
- Identify feasible internal, external and hybrid delivery approaches
- Locate the last similar project's lessons report
Explanation
Correct Answer
B:Examine lessons captured from supplier procurement and handover. Organizational learning is being separated from planned future stage work. The resulting action would be: Summarize relevant lessons and actions with the stage-boundary report.
Incorrect Answers
A:Verify the supplier license status and its effect on planned products. That investigation addresses risk warning ignored until stage end; for the stated decision, examine examine lessons captured from supplier procurement and handover.
C:Identify feasible internal, external and hybrid delivery approaches. That investigation addresses supplier selection before approach defined; for the stated decision, examine examine lessons captured from supplier procurement and handover.
D:Locate the last similar project's lessons report. That investigation addresses early lessons from similar initiative; for the stated decision, examine examine lessons captured from supplier procurement and handover.
Question 1117
A project manager encounters this situation: A pilot was low risk, but the rollout stage introduces major personal-data exposure; the project manager copies the old risk register into the new plan unchanged. Which action most appropriately applies PRINCE2 7?
- Treat startup approval as authorization for initiation only and seek separate project authorization later
- Reassess risks and treatment in the next-stage planning package
- Update the risk response and take authorized protective action during the current stage
- Define and authorize the risk management approach within the initiation work
Explanation
Correct Answer
B:Reassess risks and treatment in the next-stage planning package. The future stage has a materially different exposure not included in authorization evidence. Stage-boundary review should reassess changing risk as project work progresses.
Incorrect Answers
A:Treat startup approval as authorization for initiation only and seek separate project authorization later. It applies to premature authorization of whole project; the current decision depends on this finding: The future stage has a materially different exposure not included in authorization evidence.
C:Update the risk response and take authorized protective action during the current stage. It applies to risk warning ignored until stage end; the current decision depends on this finding: The future stage has a materially different exposure not included in authorization evidence.
D:Define and authorize the risk management approach within the initiation work. It applies to risk approach written after threats arise; the current decision depends on this finding: The future stage has a materially different exposure not included in authorization evidence.
Question 1118
An assurance reviewer investigates: A pilot was low risk, but the rollout stage introduces major personal-data exposure; the project manager copies the old risk register into the new plan unchanged. Which root cause is most consistent with the evidence?
- Risk decisions depend on inconsistent informal judgments
- Risk control is being treated as a periodic stage-boundary activity only
- The future stage has a materially different exposure not included in authorization evidence
- Initiation authorization is being confused with full delivery investment approval
Explanation
Correct Answer
C:The future stage has a materially different exposure not included in authorization evidence. That cause fits the described evidence. The relevant governance rule is: Stage-boundary review should reassess changing risk as project work progresses. The appropriate response would be to reassess risks and treatment in the next-stage planning package.
Incorrect Answers
A:Risk decisions depend on inconsistent informal judgments. This could explain a different issue concerning risk approach written after threats arise, but the reported conditions instead indicate: The future stage has a materially different exposure not included in authorization evidence.
B:Risk control is being treated as a periodic stage-boundary activity only. This could explain a different issue concerning risk warning ignored until stage end, but the reported conditions instead indicate: The future stage has a materially different exposure not included in authorization evidence.
D:Initiation authorization is being confused with full delivery investment approval. This could explain a different issue concerning premature authorization of whole project, but the reported conditions instead indicate: The future stage has a materially different exposure not included in authorization evidence.
Question 1119
A product or management action is said to resolve: A pilot was low risk, but the rollout stage introduces major personal-data exposure; the project manager copies the old risk register into the new plan unchanged. Which verification is strongest?
- Current stage controls reflect a feasible response and updated exposure
- The new risk register and stage plan address rollout-specific threats
- The board separately considers initiation outputs before releasing major delivery commitment
- The PID documents a coherent risk method and responsibilities
Explanation
Correct Answer
B:The new risk register and stage plan address rollout-specific threats. This is the observable outcome expected after the action: Reassess risks and treatment in the next-stage planning package. It tests the weakness that the future stage has a materially different exposure not included in authorization evidence.
Incorrect Answers
A:Current stage controls reflect a feasible response and updated exposure. That would verify risk warning ignored until stage end, not the outcome at issue. The evidence needed for this situation is: The new risk register and stage plan address rollout-specific threats.
C:The board separately considers initiation outputs before releasing major delivery commitment. That would verify premature authorization of whole project, not the outcome at issue. The evidence needed for this situation is: The new risk register and stage plan address rollout-specific threats.
D:The PID documents a coherent risk method and responsibilities. That would verify risk approach written after threats arise, not the outcome at issue. The evidence needed for this situation is: The new risk register and stage plan address rollout-specific threats.
Question 1120
A board wants to understand the governance reasoning behind addressing: A pilot was low risk, but the rollout stage introduces major personal-data exposure; the project manager copies the old risk register into the new plan unchanged. Which principle best fits?
- Controlling a stage includes managing risks when information changes
- Initiation sets project-wide risk governance before routine delivery
- Starting up and initiating establish progressively stronger authorization evidence
- Stage-boundary review should reassess changing risk as project work progresses
Explanation
Correct Answer
D:Stage-boundary review should reassess changing risk as project work progresses. This principle matters here because the future stage has a materially different exposure not included in authorization evidence. The response should tackle the stated project-control deficiency.
Incorrect Answers
A:Controlling a stage includes managing risks when information changes. That principle is more directly associated with risk warning ignored until stage end. The present case concerns the weakness that the future stage has a materially different exposure not included in authorization evidence.
B:Initiation sets project-wide risk governance before routine delivery. That principle is more directly associated with risk approach written after threats arise. The present case concerns the weakness that the future stage has a materially different exposure not included in authorization evidence.
C:Starting up and initiating establish progressively stronger authorization evidence. That principle is more directly associated with premature authorization of whole project. The present case concerns the weakness that the future stage has a materially different exposure not included in authorization evidence.
PRINCE2 7 Practitioner Practice Tests