Question 1050
For this project problem—A project manager reports spending as under budget while the cost-to-complete forecast shows an imminent stage overrun—which initial review would most directly focus the response?
Explanation
Correct Answer
Compare remaining supplier commitments and work with budget headroom. Current actual spend is being confused with total forecast stage cost. The resulting action would be: Use earned delivery evidence and the updated cost forecast to determine corrective or exception action.
Incorrect Answers
Examine lessons captured from supplier procurement and handover. That investigation addresses stage report omits lessons; for the stated decision, compare remaining supplier commitments and work with budget headroom.
Compare the end stage report with outstanding quality register findings. That investigation addresses product status at boundary overstated; for the stated decision, compare remaining supplier commitments and work with budget headroom.
Examine what funding and scope the board actually authorized. That investigation addresses premature authorization of whole project; for the stated decision, compare remaining supplier commitments and work with budget headroom.



PRINCE2 7 Practitioner Practice Tests