Question 1030
Which PRINCE2 management principle or mechanism best explains the appropriate response to: A development team marks a product finished and asks for new work, but the project manager never checks acceptance evidence?
- Managing product delivery includes delivering completed work packages, not merely constructing outputs
- Stage control monitors work package results against authorized product descriptions
- Managing product delivery begins with accepting authorized work
- Team managers deliver agreed products rather than set unapproved project requirements
Explanation
Correct Answer
B:Stage control monitors work package results against authorized product descriptions. This principle matters here because delivery declarations are accepted without product-based control evidence. The response should tackle the stated project-control deficiency.
Incorrect Answers
A:Managing product delivery includes delivering completed work packages, not merely constructing outputs. That principle is more directly associated with team deliverable ready but not handed over. The present case concerns the weakness that delivery declarations are accepted without product-based control evidence.
C:Managing product delivery begins with accepting authorized work. That principle is more directly associated with team starts work without agreement. The present case concerns the weakness that delivery declarations are accepted without product-based control evidence.
D:Team managers deliver agreed products rather than set unapproved project requirements. That principle is more directly associated with team manager changes acceptance criteria. The present case concerns the weakness that delivery declarations are accepted without product-based control evidence.
Question 1031
A lessons review covers: A development team marks a product finished and asks for new work, but the project manager never checks acceptance evidence. What future working practice should be adopted?
- Use a work-package acceptance checklist for each team assignment
- Reconfirm acceptance criteria with each work package
- Require product evidence before closing delegated work
- Use a formal package completion and evidence checklist
Explanation
Correct Answer
C:Require product evidence before closing delegated work. That preventive control addresses a repeated failure in which delivery declarations are accepted without product-based control evidence. Effectiveness can be checked by: Product completion is supported by agreed quality and acceptance records.
Incorrect Answers
A:Use a work-package acceptance checklist for each team assignment. It can prevent team starts work without agreement, but it does not control the stated recurrence risk: Delivery declarations are accepted without product-based control evidence.
B:Reconfirm acceptance criteria with each work package. It can prevent team manager changes acceptance criteria, but it does not control the stated recurrence risk: Delivery declarations are accepted without product-based control evidence.
D:Use a formal package completion and evidence checklist. It can prevent team deliverable ready but not handed over, but it does not control the stated recurrence risk: Delivery declarations are accepted without product-based control evidence.
Question 1032
A project manager must triage the following issue: A development team marks a product finished and asks for new work, but the project manager never checks acceptance evidence. What initial investigation best distinguishes the causes?
- Check which accepted products remain unreported to the project manager
- Inspect whether the request includes scope, quality and progress controls
- Compare the team test plan with approved product descriptions
- Examine the relevant quality register entry and product description
Explanation
Correct Answer
D:Examine the relevant quality register entry and product description. Delivery declarations are accepted without product-based control evidence. The resulting action would be: Review the work package's completed products and quality results before confirming completion.
Incorrect Answers
A:Check which accepted products remain unreported to the project manager. That investigation addresses team deliverable ready but not handed over; for the stated decision, examine examine the relevant quality register entry and product description.
B:Inspect whether the request includes scope, quality and progress controls. That investigation addresses team starts work without agreement; for the stated decision, examine examine the relevant quality register entry and product description.
C:Compare the team test plan with approved product descriptions. That investigation addresses team manager changes acceptance criteria; for the stated decision, examine examine the relevant quality register entry and product description.
Question 1033
A project board needs to respond to the following situation: An early warning shows the chosen supplier may lose a critical license midstage, but the project manager postpones all response until the next boundary. Which next action is strongest?
- Update the risk response and take authorized protective action during the current stage
- Summarize relevant lessons and actions with the stage-boundary report
- Notify the project manager promptly of the work package forecast exception
- Confirm post-project benefits review ownership and timing with the operational business
Explanation
Correct Answer
A:Update the risk response and take authorized protective action during the current stage. Risk control is being treated as a periodic stage-boundary activity only. Controlling a stage includes managing risks when information changes.
Incorrect Answers
B:Summarize relevant lessons and actions with the stage-boundary report. It applies to stage report omits lessons; the current decision depends on this finding: Risk control is being treated as a periodic stage-boundary activity only.
C:Notify the project manager promptly of the work package forecast exception. It applies to team forecast breaches work package tolerance; the current decision depends on this finding: Risk control is being treated as a periodic stage-boundary activity only.
D:Confirm post-project benefits review ownership and timing with the operational business. It applies to benefits review scheduled after disbanding; the current decision depends on this finding: Risk control is being treated as a periodic stage-boundary activity only.
Question 1034
A stage review identifies: An early warning shows the chosen supplier may lose a critical license midstage, but the project manager postpones all response until the next boundary. Which weakness in control or decision-making is most likely?
- Delegated team tolerance has been breached without timely escalation
- Organizational learning is being separated from planned future stage work
- Outcome measurement is at risk of being abandoned when the delivery team leaves
- Risk control is being treated as a periodic stage-boundary activity only
Explanation
Correct Answer
D:Risk control is being treated as a periodic stage-boundary activity only. That cause fits the described evidence. The relevant governance rule is: Controlling a stage includes managing risks when information changes. The appropriate response would be to update the risk response and take authorized protective action during the current stage.
Incorrect Answers
A:Delegated team tolerance has been breached without timely escalation. This could explain a different issue concerning team forecast breaches work package tolerance, but the reported conditions instead indicate: Risk control is being treated as a periodic stage-boundary activity only.
B:Organizational learning is being separated from planned future stage work. This could explain a different issue concerning stage report omits lessons, but the reported conditions instead indicate: Risk control is being treated as a periodic stage-boundary activity only.
C:Outcome measurement is at risk of being abandoned when the delivery team leaves. This could explain a different issue concerning benefits review scheduled after disbanding, but the reported conditions instead indicate: Risk control is being treated as a periodic stage-boundary activity only.
Question 1035
An assurance reviewer is testing the response to: An early warning shows the chosen supplier may lose a critical license midstage, but the project manager postpones all response until the next boundary. Which result should be checked?
- The project manager is informed early enough to choose appropriate control action
- The next stage plan reflects documented lessons from the preceding stage
- Current stage controls reflect a feasible response and updated exposure
- A named owner accepts a review date and baseline measures for waiting times
Explanation
Correct Answer
C:Current stage controls reflect a feasible response and updated exposure. This is the observable outcome expected after the action: Update the risk response and take authorized protective action during the current stage. It tests the weakness that risk control is being treated as a periodic stage-boundary activity only.
Incorrect Answers
A:The project manager is informed early enough to choose appropriate control action. That would verify team forecast breaches work package tolerance, not the outcome at issue. The evidence needed for this situation is: Current stage controls reflect a feasible response and updated exposure.
B:The next stage plan reflects documented lessons from the preceding stage. That would verify stage report omits lessons, not the outcome at issue. The evidence needed for this situation is: Current stage controls reflect a feasible response and updated exposure.
D:A named owner accepts a review date and baseline measures for waiting times. That would verify benefits review scheduled after disbanding, not the outcome at issue. The evidence needed for this situation is: Current stage controls reflect a feasible response and updated exposure.
Question 1036
During application of PRINCE2 7, what governing idea is illustrated by: An early warning shows the chosen supplier may lose a critical license midstage, but the project manager postpones all response until the next boundary?
- Controlling a stage includes managing risks when information changes
- Closure should preserve post-project benefits management arrangements
- A team manager must raise forecast work-package exceptions at the correct level
- Stage boundaries are opportunities to learn before the next investment decision
Explanation
Correct Answer
A:Controlling a stage includes managing risks when information changes. This principle matters here because risk control is being treated as a periodic stage-boundary activity only. The response should tackle the stated project-control deficiency.
Incorrect Answers
B:Closure should preserve post-project benefits management arrangements. That principle is more directly associated with benefits review scheduled after disbanding. The present case concerns the weakness that risk control is being treated as a periodic stage-boundary activity only.
C:A team manager must raise forecast work-package exceptions at the correct level. That principle is more directly associated with team forecast breaches work package tolerance. The present case concerns the weakness that risk control is being treated as a periodic stage-boundary activity only.
D:Stage boundaries are opportunities to learn before the next investment decision. That principle is more directly associated with stage report omits lessons. The present case concerns the weakness that risk control is being treated as a periodic stage-boundary activity only.
Question 1037
The project resolved this issue: An early warning shows the chosen supplier may lose a critical license midstage, but the project manager postpones all response until the next boundary. Which enduring preventive control would most directly reduce recurrence?
- Include benefits handover in end project approval materials
- Monitor forecast-to-tolerance continuously for critical packages
- Require lessons-log review in boundary planning
- Review major risk indicators at checkpoint meetings
Explanation
Correct Answer
D:Review major risk indicators at checkpoint meetings. That preventive control addresses a repeated failure in which risk control is being treated as a periodic stage-boundary activity only. Effectiveness can be checked by: Current stage controls reflect a feasible response and updated exposure.
Incorrect Answers
A:Include benefits handover in end project approval materials. It can prevent benefits review scheduled after disbanding, but it does not control the stated recurrence risk: Risk control is being treated as a periodic stage-boundary activity only.
B:Monitor forecast-to-tolerance continuously for critical packages. It can prevent team forecast breaches work package tolerance, but it does not control the stated recurrence risk: Risk control is being treated as a periodic stage-boundary activity only.
C:Require lessons-log review in boundary planning. It can prevent stage report omits lessons, but it does not control the stated recurrence risk: Risk control is being treated as a periodic stage-boundary activity only.
Question 1038
An assurance reviewer begins examining: An early warning shows the chosen supplier may lose a critical license midstage, but the project manager postpones all response until the next boundary. Which evidence should they inspect first?
- Examine lessons captured from supplier procurement and handover
- Compare team delivery estimates with authorized work package tolerance
- Read the benefits management approach for the review schedule and responsible owner
- Verify the supplier license status and its effect on planned products
Explanation
Correct Answer
D:Verify the supplier license status and its effect on planned products. Risk control is being treated as a periodic stage-boundary activity only. The resulting action would be: Update the risk response and take authorized protective action during the current stage.
Incorrect Answers
A:Examine lessons captured from supplier procurement and handover. That investigation addresses stage report omits lessons; for the stated decision, verify the supplier license status and its effect on planned products.
B:Compare team delivery estimates with authorized work package tolerance. That investigation addresses team forecast breaches work package tolerance; for the stated decision, verify the supplier license status and its effect on planned products.
C:Read the benefits management approach for the review schedule and responsible owner. That investigation addresses benefits review scheduled after disbanding; for the stated decision, verify the supplier license status and its effect on planned products.
Question 1039
During a project review, the team reports: A project manager moves testing responsibilities from one supplier team to another but does not amend their agreed work packages. What is the best authorized corrective action?
- Coordinate work against the accepted work package and assign the specified integration quality activities
- Agree and accept a controlled work package with the project manager before committing the team
- Notify the project manager promptly of the work package forecast exception
- Negotiate and authorize the changed work package terms with affected teams
Explanation
Correct Answer
D:Negotiate and authorize the changed work package terms with affected teams. Delegated responsibilities no longer match agreed assignments. Work package control depends on clear, current agreements.
Incorrect Answers
A:Coordinate work against the accepted work package and assign the specified integration quality activities. It applies to subcontractor tasks not coordinated; the current decision depends on this finding: Delegated responsibilities no longer match agreed assignments.
B:Agree and accept a controlled work package with the project manager before committing the team. It applies to team starts work without agreement; the current decision depends on this finding: Delegated responsibilities no longer match agreed assignments.
C:Notify the project manager promptly of the work package forecast exception. It applies to team forecast breaches work package tolerance; the current decision depends on this finding: Delegated responsibilities no longer match agreed assignments.
Question 1040
The project manager wants to understand why this occurred: A project manager moves testing responsibilities from one supplier team to another but does not amend their agreed work packages. What is the best diagnosis?
- Delegated execution has no clear internal coordination of responsibilities
- Delegated team tolerance has been breached without timely escalation
- Delegated responsibilities no longer match agreed assignments
- Informal assignment lacks the delivery terms needed for accountable performance
Explanation
Correct Answer
C:Delegated responsibilities no longer match agreed assignments. That cause fits the described evidence. The relevant governance rule is: Work package control depends on clear, current agreements. The appropriate response would be to negotiate and authorize the changed work package terms with affected teams.
Incorrect Answers
A:Delegated execution has no clear internal coordination of responsibilities. This could explain a different issue concerning subcontractor tasks not coordinated, but the reported conditions instead indicate: Delegated responsibilities no longer match agreed assignments.
B:Delegated team tolerance has been breached without timely escalation. This could explain a different issue concerning team forecast breaches work package tolerance, but the reported conditions instead indicate: Delegated responsibilities no longer match agreed assignments.
D:Informal assignment lacks the delivery terms needed for accountable performance. This could explain a different issue concerning team starts work without agreement, but the reported conditions instead indicate: Delegated responsibilities no longer match agreed assignments.