Question 1060
An instructor asks why the proposed management control is justified for: A delivery team decides to reduce a product's resilience target to save time without seeking the project manager's authorization. Which explanation is most relevant?
Explanation
Correct Answer
Team managers deliver agreed products rather than set unapproved project requirements. This principle matters here because delivery discretion is being used to change baselined requirements. The response should tackle the stated project-control deficiency.
Incorrect Answers
Closure should preserve post-project benefits management arrangements. That principle is more directly associated with benefits review scheduled after disbanding. The present case concerns the weakness that delivery discretion is being used to change baselined requirements.
Stage control monitors work package results against authorized product descriptions. That principle is more directly associated with completed product not checked. The present case concerns the weakness that delivery discretion is being used to change baselined requirements.
Starting up and initiating establish progressively stronger authorization evidence. That principle is more directly associated with premature authorization of whole project. The present case concerns the weakness that delivery discretion is being used to change baselined requirements.



PRINCE2 7 Practitioner Practice Tests