Question 410
The audit team proposes this response: Design record counts, control totals and business-rule reconciliation across conversion stages. For the situation—A migration plan copies millions of account balances but has no source-to-target reconciliation controls. Which evidence would BEST demonstrate that the response was effective?
- Trace original requirements and audit issues to acceptance evidence, owners and dates.
- Inspect requirements-to-design-to-test mapping and change history.
- Inspect governance charters, oversight reports and evidence of issue closure review.
- Reperform sampled balances and reconcile source-target totals including rejected records.
Explanation
Correct Answer
D:Data migration assurance must address completeness and accuracy, not just successful file transfer. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:Post-implementation assurance requires transparent treatment of residual exceptions. The relevant evidence instead is: Reperform sampled balances and reconcile source-target totals including rejected records.
B:Development methodology must maintain consistency between requirements, build and validation. The acceptance criterion here is: Reperform sampled balances and reconcile source-target totals including rejected records.
C:The auditor should retain enough source context to reproduce the conclusion. What must be demonstrated is: Reperform sampled balances and reconcile source-target totals including rejected records.
Question 411
In another organization, a data conversion changes currency precision and loses small transaction amounts. Which assurance principle BEST explains the audit implication?
- Agile delivery can support strong controls when assurance activities are integrated into each iteration.
- Controlled project change management protects objectives and assurance scope from unexamined drift.
- A post-implementation review checks whether delivered systems achieved expected business value.
- Data migration assurance must address completeness and accuracy, not just successful file transfer.
Explanation
Correct Answer
D:This principle explains the control or assurance implication in the second, independent scenario. Data migration assurance must address completeness and accuracy, not just successful file transfer. The auditor should relate that principle to the observed evidence.
Incorrect Answers
A:This is a valid consideration in system development methodologies; the scenario instead turns on a different, more specific assurance requirement.
B:This is a valid consideration in project governance and management; the scenario instead turns on a different, more specific assurance requirement.
C:This is a valid consideration in post-implementation review; the scenario instead turns on a different, more specific assurance requirement.
Question 412
In another organization, a data conversion changes currency precision and loses small transaction amounts. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- Matching the number of copied files cannot prove that converted business values are correct.
- A vendor's declaration of completion is not a substitute for customer acceptance.
- A technically successful deployment is not evidence that approval controls were followed.
- Validating user input cannot ensure pricing logic is protected from unauthorized modification.
Explanation
Correct Answer
A:Matching the number of copied files cannot prove that converted business values are correct. The underlying issue is that data migration assurance must address completeness and accuracy, not just successful file transfer.
Incorrect Answers
B:That caution could matter when assessing system development methodologies, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing implementation configuration and release management, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing control identification and design, but it is not the most immediate unsupported assumption in this case.
Question 413
A company moves a payment application but ignores external settlement messages that arrive during cutover. Which response should an IS auditor recommend as MOST appropriate?
- Define testable control objectives, owners, enforcement and exception evidence during design.
- Evaluate that chosen development methodology retains traceable requirements and quality gates.
- Map risks to application controls over authorization, processing integrity and configuration changes.
- Plan transaction cutover, interface quiescence or controlled replay and end-to-end reconciliation.
Explanation
Correct Answer
D:Migration control must account for transactions occurring between old and new states. The most directly responsive audit action is: Plan transaction cutover, interface quiescence or controlled replay and end-to-end reconciliation. Verification should include: Check in-flight queue counts, sequence identifiers and business confirmation after cutover.
Incorrect Answers
A:Controls can be assured only when the design specifies the risk, behavior and evidence. The appropriate comparison is: Plan transaction cutover, interface quiescence or controlled replay and end-to-end reconciliation.
B:Agile delivery can support strong controls when assurance activities are integrated into each iteration. The relevant evidence instead is: Plan transaction cutover, interface quiescence or controlled replay and end-to-end reconciliation.
C:Application control design must protect the integrity of both inputs and business rules. The acceptance criterion here is: Plan transaction cutover, interface quiescence or controlled replay and end-to-end reconciliation.
Question 414
The audit team proposes this response: Plan transaction cutover, interface quiescence or controlled replay and end-to-end reconciliation. For the situation—A company moves a payment application but ignores external settlement messages that arrive during cutover. Which evidence would BEST demonstrate that the response was effective?
- Inspect privacy assessment, dependency testing, skills coverage and regulatory constraints.
- Attempt authorized and unauthorized configuration changes and recompute selected transactions.
- Check in-flight queue counts, sequence identifiers and business confirmation after cutover.
- Reperform key benefit and cost scenarios under credible adverse inputs.
Explanation
Correct Answer
C:Migration control must account for transactions occurring between old and new states. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:Feasibility is multidimensional and a proposal can be impossible even when code can be built. The needed step here is to check in-flight queue counts, sequence identifiers and business confirmation after cutover.
B:Application control design must protect the integrity of both inputs and business rules. The appropriate remedy is to check in-flight queue counts, sequence identifiers and business confirmation after cutover.
D:Business-case choices require assessment of uncertainty and risk, not only one-point forecasts. Instead, the response must check in-flight queue counts, sequence identifiers and business confirmation after cutover.
Question 415
At a separate firm, a database migration excludes delayed interfaces, leaving transactions in flight. Which assurance principle BEST explains the audit implication?
- Controls can be assured only when the design specifies the risk, behavior and evidence.
- System readiness requires representative end-to-end testing beyond individual component correctness.
- Release management should limit blast radius and preserve recovery options.
- Migration control must account for transactions occurring between old and new states.
Explanation
Correct Answer
D:This principle explains the control or assurance implication in the second, independent scenario. Migration control must account for transactions occurring between old and new states. The auditor should relate that principle to the observed evidence.
Incorrect Answers
A:This is a valid consideration in control identification and design; the scenario instead turns on a different, more specific assurance requirement.
B:This is a valid consideration in system readiness and implementation testing; the scenario instead turns on a different, more specific assurance requirement.
C:This is a valid consideration in implementation configuration and release management; the scenario instead turns on a different, more specific assurance requirement.
Question 416
At a separate firm, a database migration excludes delayed interfaces, leaving transactions in flight. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- Encryption does not by itself prevent an authorized insider from approving their own transaction.
- A clean database snapshot is not proof that all in-flight messages were processed.
- An early signed-off specification is not always current after legitimate business changes.
- An optimistic payback number is not an objective guarantee of value.
Explanation
Correct Answer
B:A clean database snapshot is not proof that all in-flight messages were processed. The underlying issue is that migration control must account for transactions occurring between old and new states.
Incorrect Answers
A:That caution could matter when assessing control identification and design, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing system development methodologies, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing business case and feasibility analysis, but it is not the most immediate unsupported assumption in this case.
Question 417
A legacy system is decommissioned immediately after cutover without a tested return path. Which response should an IS auditor recommend as MOST appropriate?
- Define validated rollback, retention and cutover decision criteria before retiring legacy services.
- Evaluate technical, legal, operational and schedule feasibility separately before approval.
- Identify fraud and error risks and design preventive segregation or approved compensating controls.
- Include direct, indirect, transition and recurring costs in financial feasibility analysis.
Explanation
Correct Answer
A:Migration risk requires a feasible recovery path until converted services are accepted. The most directly responsive audit action is: Define validated rollback, retention and cutover decision criteria before retiring legacy services. Verification should include: Inspect go/no-go logs, restore exercise and controlled source data preservation.
Incorrect Answers
B:Feasibility is multidimensional and a proposal can be impossible even when code can be built. The relevant control is to define validated rollback, retention and cutover decision criteria before retiring legacy services.
C:Control design must address the relevant risk path, not rely on an unrelated security feature. The needed step here is to define validated rollback, retention and cutover decision criteria before retiring legacy services.
D:Financial feasibility depends on realistic complete costs and measurable benefit timing. The appropriate remedy is to define validated rollback, retention and cutover decision criteria before retiring legacy services.
Question 418
The audit team proposes this response: Define validated rollback, retention and cutover decision criteria before retiring legacy services. For the situation—A legacy system is decommissioned immediately after cutover without a tested return path. Which evidence would BEST demonstrate that the response was effective?
- Compare baseline and actual service measures, user outcomes and issue closure against commitments.
- Compare live configuration to signed baseline and version-controlled deployment artifacts.
- Inspect go/no-go logs, restore exercise and controlled source data preservation.
- Inspect vendor test artifacts, contractual criteria and enterprise acceptance records.
Explanation
Correct Answer
C:Migration risk requires a feasible recovery path until converted services are accepted. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:The auditor should retain enough source context to reproduce the conclusion. Instead, the response must inspect go/no-go logs, restore exercise and controlled source data preservation.
B:Baseline configuration management supports traceability, change impact and reliable recovery. The relevant control is to inspect go/no-go logs, restore exercise and controlled source data preservation.
D:Using external developers does not transfer accountability for enterprise requirements and assurance. The needed step here is to inspect go/no-go logs, restore exercise and controlled source data preservation.
Question 419
In another business, migration support discovers an unrecoverable mapping error after source archives were deleted. Which assurance principle BEST explains the audit implication?
- Migration risk requires a feasible recovery path until converted services are accepted.
- Agile delivery can support strong controls when assurance activities are integrated into each iteration.
- Segregation in release management limits unauthorized or unreviewed production changes.
- Feasibility is multidimensional and a proposal can be impossible even when code can be built.
Explanation
Correct Answer
A:This principle explains the control or assurance implication in the second, independent scenario. Migration risk requires a feasible recovery path until converted services are accepted. The auditor should relate that principle to the observed evidence.
Incorrect Answers
B:This is a valid consideration in system development methodologies; the scenario instead turns on a different, more specific assurance requirement.
C:This is a valid consideration in implementation configuration and release management; the scenario instead turns on a different, more specific assurance requirement.
D:This is a valid consideration in business case and feasibility analysis; the scenario instead turns on a different, more specific assurance requirement.
Question 420
In another business, migration support discovers an unrecoverable mapping error after source archives were deleted. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- Completing the deployment wizard does not make rollback or source evidence unnecessary.
- A technically successful deployment is not evidence that approval controls were followed.
- A vague security requirement cannot be reliably tested for effectiveness.
- Encryption does not by itself prevent an authorized insider from approving their own transaction.
Explanation
Correct Answer
A:Completing the deployment wizard does not make rollback or source evidence unnecessary. The underlying issue is that migration risk requires a feasible recovery path until converted services are accepted.
Incorrect Answers
B:That caution could matter when assessing implementation configuration and release management, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing control identification and design, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing control identification and design, but it is not the most immediate unsupported assumption in this case.
Certified Information Systems Auditor (CISA) Practice Tests