Question 390
The audit team proposes this response: Escalate unresolved material defects and require qualified, documented acceptance or remediation before go-live. For the situation—A go-live gate is approved despite open critical defects and no documented workaround or risk acceptance. Which evidence would BEST demonstrate that the response was effective?
- Inspect vendor test artifacts, contractual criteria and enterprise acceptance records.
- Inspect go/no-go logs, restore exercise and controlled source data preservation.
- Reconcile management summaries with defect, dependency, budget and risk records.
- Inspect defect severity, owner decisions, workarounds and readiness checklist.
Explanation
Correct Answer
D:Deployment approval should reflect actual residual risk against pre-agreed go-live criteria. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:Using external developers does not transfer accountability for enterprise requirements and assurance. The needed step here is to inspect defect severity, owner decisions, workarounds and readiness checklist.
B:Migration risk requires a feasible recovery path until converted services are accepted. The appropriate remedy is to inspect defect severity, owner decisions, workarounds and readiness checklist.
C:Effective project governance requires transparent indicators beyond schedule color codes. Instead, the response must inspect defect severity, owner decisions, workarounds and readiness checklist.
Question 391
At a second firm, a release manager treats remaining security findings as cosmetic because the schedule is urgent. Which assurance principle BEST explains the audit implication?
- Application control design must protect the integrity of both inputs and business rules.
- Deployment approval should reflect actual residual risk against pre-agreed go-live criteria.
- Release management should limit blast radius and preserve recovery options.
- Controls can be assured only when the design specifies the risk, behavior and evidence.
Explanation
Correct Answer
B:This principle explains the control or assurance implication in the second, independent scenario. Deployment approval should reflect actual residual risk against pre-agreed go-live criteria. The auditor should relate that principle to the observed evidence.
Incorrect Answers
A:This is a valid consideration in control identification and design; the scenario instead turns on a different, more specific assurance requirement.
C:This is a valid consideration in implementation configuration and release management; the scenario instead turns on a different, more specific assurance requirement.
D:This is a valid consideration in control identification and design; the scenario instead turns on a different, more specific assurance requirement.
Question 392
At a second firm, a release manager treats remaining security findings as cosmetic because the schedule is urgent. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- A fixed go-live date does not make a critical unresolved defect acceptable.
- A high-priority patch does not justify skipping all compatibility and rollback controls.
- Project-team self-certification cannot always replace independent program-level oversight.
- A single prelaunch test pass is not conclusive proof of sustained production effectiveness.
Explanation
Correct Answer
A:A fixed go-live date does not make a critical unresolved defect acceptable. The underlying issue is that deployment approval should reflect actual residual risk against pre-agreed go-live criteria.
Incorrect Answers
B:That caution could matter when assessing implementation configuration and release management, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing project governance and management, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing post-implementation review, but it is not the most immediate unsupported assumption in this case.
Question 393
A disaster recovery procedure is listed in the go-live plan but has not been executed under realistic load. Which response should an IS auditor recommend as MOST appropriate?
- Evaluate business case assumptions, measurable benefits, total costs and feasibility evidence.
- Test recovery and rollback using realistic service scenarios prior to production cutover.
- Define validated rollback, retention and cutover decision criteria before retiring legacy services.
- Design record counts, control totals and business-rule reconciliation across conversion stages.
Explanation
Correct Answer
B:Operational readiness includes demonstrated recovery capability, not only a written procedure. The most directly responsive audit action is: Test recovery and rollback using realistic service scenarios prior to production cutover. Verification should include: Review timed exercises, data integrity checks and return-to-service evidence.
Incorrect Answers
A:A sound business case measures achievable outcomes and full lifecycle cost rather than features alone. The relevant control is to test recovery and rollback using realistic service scenarios prior to production cutover.
C:Migration risk requires a feasible recovery path until converted services are accepted. The needed step here is to test recovery and rollback using realistic service scenarios prior to production cutover.
D:Data migration assurance must address completeness and accuracy, not just successful file transfer. The appropriate remedy is to test recovery and rollback using realistic service scenarios prior to production cutover.
Question 394
The audit team proposes this response: Test recovery and rollback using realistic service scenarios prior to production cutover. For the situation—A disaster recovery procedure is listed in the go-live plan but has not been executed under realistic load. Which evidence would BEST demonstrate that the response was effective?
- Compare post-go-live incident metrics and peak-load behavior against acceptance thresholds.
- Inspect requirements-to-design-to-test mapping and change history.
- Trace sampled scope decisions to designated business owners, approvals and baseline changes.
- Review timed exercises, data integrity checks and return-to-service evidence.
Explanation
Correct Answer
D:Operational readiness includes demonstrated recovery capability, not only a written procedure. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:This observation could inform an assessment of post-implementation review, but it would not directly demonstrate the corrective action in the present case.
B:Development methodology must maintain consistency between requirements, build and validation. Instead, the response must review timed exercises, data integrity checks and return-to-service evidence.
C:Project governance must connect change decisions to authorized business objectives and responsibilities. The relevant control is to review timed exercises, data integrity checks and return-to-service evidence.
Question 395
At another enterprise, rollback documents exist but the team has never tested restoration from a failed release. Which assurance principle BEST explains the audit implication?
- Application control design must protect the integrity of both inputs and business rules.
- A sound business case measures achievable outcomes and full lifecycle cost rather than features alone.
- Baseline configuration management supports traceability, change impact and reliable recovery.
- Operational readiness includes demonstrated recovery capability, not only a written procedure.
Explanation
Correct Answer
D:This principle explains the control or assurance implication in the second, independent scenario. Operational readiness includes demonstrated recovery capability, not only a written procedure. The auditor should relate that principle to the observed evidence.
Incorrect Answers
A:This is a valid consideration in control identification and design; the scenario instead turns on a different, more specific assurance requirement.
B:This is a valid consideration in business case and feasibility analysis; the scenario instead turns on a different, more specific assurance requirement.
C:This is a valid consideration in implementation configuration and release management; the scenario instead turns on a different, more specific assurance requirement.
Question 396
At another enterprise, rollback documents exist but the team has never tested restoration from a failed release. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- Passing application tests does not validate a package that differs from the reviewed build.
- A recovery document alone does not prove successful restoration when needed.
- A clean database snapshot is not proof that all in-flight messages were processed.
- Meeting a deployment deadline does not by itself establish benefit realization.
Explanation
Correct Answer
B:A recovery document alone does not prove successful restoration when needed. The underlying issue is that operational readiness includes demonstrated recovery capability, not only a written procedure.
Incorrect Answers
A:That caution could matter when assessing system development methodologies, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing system migration, infrastructure deployment, and data conversion, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing post-implementation review, but it is not the most immediate unsupported assumption in this case.
Question 397
A developer uses the same credentials to build software and approve its production deployment. Which response should an IS auditor recommend as MOST appropriate?
- Reconcile completion deliverables, unresolved risks and assigned follow-up owners before project closure.
- Define testable control objectives, owners, enforcement and exception evidence during design.
- Implement role separation and approved promotion steps for production configuration and releases.
- Plan transaction cutover, interface quiescence or controlled replay and end-to-end reconciliation.
Explanation
Correct Answer
C:Segregation in release management limits unauthorized or unreviewed production changes. The most directly responsive audit action is: Implement role separation and approved promotion steps for production configuration and releases. Verification should include: Trace a sample release to distinct maker, reviewer, deployment identity and recorded approval.
Incorrect Answers
A:Post-implementation assurance requires transparent treatment of residual exceptions. The needed step here is to implement role separation and approved promotion steps for production configuration and releases.
B:Controls can be assured only when the design specifies the risk, behavior and evidence. The appropriate remedy is to implement role separation and approved promotion steps for production configuration and releases.
D:Migration control must account for transactions occurring between old and new states. Instead, the response must implement role separation and approved promotion steps for production configuration and releases.
Question 398
The audit team proposes this response: Implement role separation and approved promotion steps for production configuration and releases. For the situation—A developer uses the same credentials to build software and approve its production deployment. Which evidence would BEST demonstrate that the response was effective?
- Inspect governance charters, oversight reports and evidence of issue closure review.
- Recalculate total cost of ownership using documented volumes, exit costs and support requirements.
- Trace a sample release to distinct maker, reviewer, deployment identity and recorded approval.
- Inspect requirements-to-design-to-test mapping and change history.
Explanation
Correct Answer
C:Segregation in release management limits unauthorized or unreviewed production changes. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:This observation could inform an assessment of project governance and management, but it would not directly demonstrate the corrective action in the present case.
B:Financial feasibility depends on realistic complete costs and measurable benefit timing. The relevant control is to trace a sample release to distinct maker, reviewer, deployment identity and recorded approval.
D:Development methodology must maintain consistency between requirements, build and validation. The needed step here is to trace a sample release to distinct maker, reviewer, deployment identity and recorded approval.
Question 399
At another organization, no independent check exists between change creation and release authorization. Which assurance principle BEST explains the audit implication?
- Secure development requires traceability of changes and trusted software artifacts throughout delivery.
- Controls can be assured only when the design specifies the risk, behavior and evidence.
- Migration control must account for transactions occurring between old and new states.
- Segregation in release management limits unauthorized or unreviewed production changes.
Explanation
Correct Answer
D:This principle explains the control or assurance implication in the second, independent scenario. Segregation in release management limits unauthorized or unreviewed production changes. The auditor should relate that principle to the observed evidence.
Incorrect Answers
A:This is a valid consideration in system development methodologies; the scenario instead turns on a different, more specific assurance requirement.
B:This is a valid consideration in control identification and design; the scenario instead turns on a different, more specific assurance requirement.
C:This is a valid consideration in system migration, infrastructure deployment, and data conversion; the scenario instead turns on a different, more specific assurance requirement.
Question 400
At another organization, no independent check exists between change creation and release authorization. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- Encryption does not by itself prevent an authorized insider from approving their own transaction.
- A technically successful deployment is not evidence that approval controls were followed.
- A recovery document alone does not prove successful restoration when needed.
- Meeting a deployment deadline does not by itself establish benefit realization.
Explanation
Correct Answer
B:A technically successful deployment is not evidence that approval controls were followed. The underlying issue is that segregation in release management limits unauthorized or unreviewed production changes.
Incorrect Answers
A:That caution could matter when assessing control identification and design, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing system readiness and implementation testing, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing post-implementation review, but it is not the most immediate unsupported assumption in this case.
Certified Information Systems Auditor (CISA) Practice Tests