Question 380
At another marketplace, calculation parameters can be modified without authorization even though web forms validate fields. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- Matching the number of copied files cannot prove that converted business values are correct.
- Technical feasibility alone does not demonstrate an implementable compliant business solution.
- Validating user input cannot ensure pricing logic is protected from unauthorized modification.
- Closing the project financially does not automatically close its unresolved security issues.
Explanation
Correct Answer
C:Validating user input cannot ensure pricing logic is protected from unauthorized modification. The underlying issue is that application control design must protect the integrity of both inputs and business rules.
Incorrect Answers
A:That caution could matter when assessing system migration, infrastructure deployment, and data conversion, but it is not the most immediate unsupported assumption in this case.
B:That caution could matter when assessing business case and feasibility analysis, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing post-implementation review, but it is not the most immediate unsupported assumption in this case.
Question 381
A proposed automated control is defined only as the system shall be secure with no measurable behavior. Which response should an IS auditor recommend as MOST appropriate?
- Implement role separation and approved promotion steps for production configuration and releases.
- Test recovery and rollback using realistic service scenarios prior to production cutover.
- Define testable control objectives, owners, enforcement and exception evidence during design.
- Evaluate business case assumptions, measurable benefits, total costs and feasibility evidence.
Explanation
Correct Answer
C:Controls can be assured only when the design specifies the risk, behavior and evidence. The most directly responsive audit action is: Define testable control objectives, owners, enforcement and exception evidence during design. Verification should include: Inspect the control design for measurable behavior and independently executable test criteria.
Incorrect Answers
A:Segregation in release management limits unauthorized or unreviewed production changes. The appropriate remedy is to define testable control objectives, owners, enforcement and exception evidence during design.
B:Operational readiness includes demonstrated recovery capability, not only a written procedure. Instead, the response must define testable control objectives, owners, enforcement and exception evidence during design.
D:A sound business case measures achievable outcomes and full lifecycle cost rather than features alone. The relevant control is to define testable control objectives, owners, enforcement and exception evidence during design.
Question 382
The audit team proposes this response: Define testable control objectives, owners, enforcement and exception evidence during design. For the situation—A proposed automated control is defined only as the system shall be secure with no measurable behavior. Which evidence would BEST demonstrate that the response was effective?
- Inspect the control design for measurable behavior and independently executable test criteria.
- Inspect vendor test artifacts, contractual criteria and enterprise acceptance records.
- Sample user stories from approval through automated tests, security checks and production acceptance.
- Inspect privacy assessment, dependency testing, skills coverage and regulatory constraints.
Explanation
Correct Answer
A:Controls can be assured only when the design specifies the risk, behavior and evidence. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
B:Using external developers does not transfer accountability for enterprise requirements and assurance. The needed step here is to inspect the control design for measurable behavior and independently executable test criteria.
C:Agile delivery can support strong controls when assurance activities are integrated into each iteration. The appropriate remedy is to inspect the control design for measurable behavior and independently executable test criteria.
D:Feasibility is multidimensional and a proposal can be impossible even when code can be built. Instead, the response must inspect the control design for measurable behavior and independently executable test criteria.
Question 383
At a separate insurer, design reviews approve a control with no owner, failure alert or evidence requirement. Which assurance principle BEST explains the audit implication?
- Feasibility is multidimensional and a proposal can be impossible even when code can be built.
- Deployment approval should reflect actual residual risk against pre-agreed go-live criteria.
- Migration control must account for transactions occurring between old and new states.
- Controls can be assured only when the design specifies the risk, behavior and evidence.
Explanation
Correct Answer
D:This principle explains the control or assurance implication in the second, independent scenario. Controls can be assured only when the design specifies the risk, behavior and evidence. The auditor should relate that principle to the observed evidence.
Incorrect Answers
A:This is a valid consideration in business case and feasibility analysis; the scenario instead turns on a different, more specific assurance requirement.
B:This is a valid consideration in system readiness and implementation testing; the scenario instead turns on a different, more specific assurance requirement.
C:This is a valid consideration in system migration, infrastructure deployment, and data conversion; the scenario instead turns on a different, more specific assurance requirement.
Question 384
At a separate insurer, design reviews approve a control with no owner, failure alert or evidence requirement. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- Short sprints do not automatically provide effective security and compliance controls.
- An update ticket without exact configuration differences is insufficient reconstruction evidence.
- A vague security requirement cannot be reliably tested for effectiveness.
- A senior technical sponsor does not replace documented approval by an accountable business owner.
Explanation
Correct Answer
C:A vague security requirement cannot be reliably tested for effectiveness. The underlying issue is that controls can be assured only when the design specifies the risk, behavior and evidence.
Incorrect Answers
A:That caution could matter when assessing system development methodologies, but it is not the most immediate unsupported assumption in this case.
B:That caution could matter when assessing implementation configuration and release management, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing project governance and management, but it is not the most immediate unsupported assumption in this case.
Question 385
A new core banking release passes unit tests but end-to-end posting across systems has never been validated. Which response should an IS auditor recommend as MOST appropriate?
- Evaluate that chosen development methodology retains traceable requirements and quality gates.
- Evaluate project governance roles, decision authority and control over scope changes.
- Reconcile completion deliverables, unresolved risks and assigned follow-up owners before project closure.
- Require integration, security, user acceptance and operational readiness testing against approved criteria.
Explanation
Correct Answer
D:System readiness requires representative end-to-end testing beyond individual component correctness. The most directly responsive audit action is: Require integration, security, user acceptance and operational readiness testing against approved criteria. Verification should include: Trace high-risk business scenarios through test results, defects and accountable signoff.
Incorrect Answers
A:Agile delivery can support strong controls when assurance activities are integrated into each iteration. The relevant control is to require integration, security, user acceptance and operational readiness testing against approved criteria.
B:Project governance must connect change decisions to authorized business objectives and responsibilities. The needed step here is to require integration, security, user acceptance and operational readiness testing against approved criteria.
C:Post-implementation assurance requires transparent treatment of residual exceptions. The appropriate remedy is to require integration, security, user acceptance and operational readiness testing against approved criteria.
Question 386
The audit team proposes this response: Require integration, security, user acceptance and operational readiness testing against approved criteria. For the situation—A new core banking release passes unit tests but end-to-end posting across systems has never been validated. Which evidence would BEST demonstrate that the response was effective?
- Check in-flight queue counts, sequence identifiers and business confirmation after cutover.
- Trace high-risk business scenarios through test results, defects and accountable signoff.
- Inspect governance charters, oversight reports and evidence of issue closure review.
- Compare baseline and actual service measures, user outcomes and issue closure against commitments.
Explanation
Correct Answer
B:System readiness requires representative end-to-end testing beyond individual component correctness. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:Migration control must account for transactions occurring between old and new states. Instead, the response must trace high-risk business scenarios through test results, defects and accountable signoff.
C:The auditor should retain enough source context to reproduce the conclusion. The relevant control is to trace high-risk business scenarios through test results, defects and accountable signoff.
D:The auditor should retain enough source context to reproduce the conclusion. The needed step here is to trace high-risk business scenarios through test results, defects and accountable signoff.
Question 387
At another service, all developers report success while business acceptance scenarios for interfaces remain unexecuted. Which assurance principle BEST explains the audit implication?
- Agile delivery can support strong controls when assurance activities are integrated into each iteration.
- Project governance must connect change decisions to authorized business objectives and responsibilities.
- System readiness requires representative end-to-end testing beyond individual component correctness.
- Controlled project change management protects objectives and assurance scope from unexamined drift.
Explanation
Correct Answer
C:This principle explains the control or assurance implication in the second, independent scenario. System readiness requires representative end-to-end testing beyond individual component correctness. The auditor should relate that principle to the observed evidence.
Incorrect Answers
A:This is a valid consideration in system development methodologies; the scenario instead turns on a different, more specific assurance requirement.
B:This is a valid consideration in project governance and management; the scenario instead turns on a different, more specific assurance requirement.
D:This is a valid consideration in project governance and management; the scenario instead turns on a different, more specific assurance requirement.
Question 388
At another service, all developers report success while business acceptance scenarios for interfaces remain unexecuted. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- Technical feasibility alone does not demonstrate an implementable compliant business solution.
- Encryption does not by itself prevent an authorized insider from approving their own transaction.
- A single prelaunch test pass is not conclusive proof of sustained production effectiveness.
- Successful unit tests do not establish that the complete service works.
Explanation
Correct Answer
D:Successful unit tests do not establish that the complete service works. The underlying issue is that system readiness requires representative end-to-end testing beyond individual component correctness.
Incorrect Answers
A:That caution could matter when assessing business case and feasibility analysis, but it is not the most immediate unsupported assumption in this case.
B:That caution could matter when assessing control identification and design, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing post-implementation review, but it is not the most immediate unsupported assumption in this case.
Question 389
A go-live gate is approved despite open critical defects and no documented workaround or risk acceptance. Which response should an IS auditor recommend as MOST appropriate?
- Escalate unresolved material defects and require qualified, documented acceptance or remediation before go-live.
- Assess secure software development, review, build integrity and environment segregation.
- Maintain approved configuration baselines and reproducible release change records.
- Review operational experience and update controls and capacity plans using actual workload evidence.
Explanation
Correct Answer
A:Deployment approval should reflect actual residual risk against pre-agreed go-live criteria. The most directly responsive audit action is: Escalate unresolved material defects and require qualified, documented acceptance or remediation before go-live. Verification should include: Inspect defect severity, owner decisions, workarounds and readiness checklist.
Incorrect Answers
B:Secure development requires traceability of changes and trusted software artifacts throughout delivery. The appropriate remedy is to escalate unresolved material defects and require qualified, documented acceptance or remediation before go-live.
C:Baseline configuration management supports traceability, change impact and reliable recovery. Instead, the response must escalate unresolved material defects and require qualified, documented acceptance or remediation before go-live.
D:Implementation success should be reassessed using real operating conditions and feedback. The relevant control is to escalate unresolved material defects and require qualified, documented acceptance or remediation before go-live.
Question 390
The audit team proposes this response: Escalate unresolved material defects and require qualified, documented acceptance or remediation before go-live. For the situation—A go-live gate is approved despite open critical defects and no documented workaround or risk acceptance. Which evidence would BEST demonstrate that the response was effective?
- Inspect vendor test artifacts, contractual criteria and enterprise acceptance records.
- Inspect go/no-go logs, restore exercise and controlled source data preservation.
- Reconcile management summaries with defect, dependency, budget and risk records.
- Inspect defect severity, owner decisions, workarounds and readiness checklist.
Explanation
Correct Answer
D:Deployment approval should reflect actual residual risk against pre-agreed go-live criteria. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:Using external developers does not transfer accountability for enterprise requirements and assurance. The needed step here is to inspect defect severity, owner decisions, workarounds and readiness checklist.
B:Migration risk requires a feasible recovery path until converted services are accepted. The appropriate remedy is to inspect defect severity, owner decisions, workarounds and readiness checklist.
C:Effective project governance requires transparent indicators beyond schedule color codes. Instead, the response must inspect defect severity, owner decisions, workarounds and readiness checklist.