Question 420
In another business, migration support discovers an unrecoverable mapping error after source archives were deleted. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- Completing the deployment wizard does not make rollback or source evidence unnecessary.
- A technically successful deployment is not evidence that approval controls were followed.
- A vague security requirement cannot be reliably tested for effectiveness.
- Encryption does not by itself prevent an authorized insider from approving their own transaction.
Explanation
Correct Answer
A:Completing the deployment wizard does not make rollback or source evidence unnecessary. The underlying issue is that migration risk requires a feasible recovery path until converted services are accepted.
Incorrect Answers
B:That caution could matter when assessing implementation configuration and release management, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing control identification and design, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing control identification and design, but it is not the most immediate unsupported assumption in this case.
Question 421
A new ERP meets the go-live milestone but promised faster invoice processing was never measured afterward. Which response should an IS auditor recommend as MOST appropriate?
- Identify fraud and error risks and design preventive segregation or approved compensating controls.
- Conduct an independent post-implementation review of benefits, control outcomes and open risks.
- Require controlled requirements traceability and update testing when the approved baseline changes.
- Recommend independent program assurance and escalation for material delivery control deficiencies.
Explanation
Correct Answer
B:A post-implementation review checks whether delivered systems achieved expected business value. The most directly responsive audit action is: Conduct an independent post-implementation review of benefits, control outcomes and open risks. Verification should include: Compare baseline and actual service measures, user outcomes and issue closure against commitments.
Incorrect Answers
A:Control design must address the relevant risk path, not rely on an unrelated security feature. What must be demonstrated is: Conduct an independent post-implementation review of benefits, control outcomes and open risks.
C:Development methodology must maintain consistency between requirements, build and validation. The appropriate comparison is: Conduct an independent post-implementation review of benefits, control outcomes and open risks.
D:Independent project assurance improves objectivity over high-impact delivery risks. The relevant evidence instead is: Conduct an independent post-implementation review of benefits, control outcomes and open risks.
Question 422
The audit team proposes this response: Conduct an independent post-implementation review of benefits, control outcomes and open risks. For the situation—A new ERP meets the go-live milestone but promised faster invoice processing was never measured afterward. Which evidence would BEST demonstrate that the response was effective?
- Inspect privacy assessment, dependency testing, skills coverage and regulatory constraints.
- Verify approved commits, build artifact hashes, automated gate results and deployment authorization.
- Compare baseline and actual service measures, user outcomes and issue closure against commitments.
- Trace high-risk business scenarios through test results, defects and accountable signoff.
Explanation
Correct Answer
C:A post-implementation review checks whether delivered systems achieved expected business value. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:Feasibility is multidimensional and a proposal can be impossible even when code can be built. The appropriate remedy is to compare baseline and actual service measures, user outcomes and issue closure against commitments.
B:Secure development requires traceability of changes and trusted software artifacts throughout delivery. Instead, the response must compare baseline and actual service measures, user outcomes and issue closure against commitments.
D:System readiness requires representative end-to-end testing beyond individual component correctness. The relevant control is to compare baseline and actual service measures, user outcomes and issue closure against commitments.
Question 423
At another enterprise, an expensive service upgrade is closed without comparing outcomes to the approved business case. Which assurance principle BEST explains the audit implication?
- A post-implementation review checks whether delivered systems achieved expected business value.
- Migration risk requires a feasible recovery path until converted services are accepted.
- Secure development requires traceability of changes and trusted software artifacts throughout delivery.
- Data migration assurance must address completeness and accuracy, not just successful file transfer.
Explanation
Correct Answer
A:This principle explains the control or assurance implication in the second, independent scenario. A post-implementation review checks whether delivered systems achieved expected business value. The auditor should relate that principle to the observed evidence.
Incorrect Answers
B:This is a valid consideration in system migration, infrastructure deployment, and data conversion; the scenario instead turns on a different, more specific assurance requirement.
C:This is a valid consideration in system development methodologies; the scenario instead turns on a different, more specific assurance requirement.
D:This is a valid consideration in system migration, infrastructure deployment, and data conversion; the scenario instead turns on a different, more specific assurance requirement.
Question 424
At another enterprise, an expensive service upgrade is closed without comparing outcomes to the approved business case. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- A green project status is not proof that major delivery risks are controlled.
- Short sprints do not automatically provide effective security and compliance controls.
- Project-team self-certification cannot always replace independent program-level oversight.
- Meeting a deployment deadline does not by itself establish benefit realization.
Explanation
Correct Answer
D:Meeting a deployment deadline does not by itself establish benefit realization. The underlying issue is that a post-implementation review checks whether delivered systems achieved expected business value.
Incorrect Answers
A:That caution could matter when assessing project governance and management, but it is not the most immediate unsupported assumption in this case.
B:That caution could matter when assessing system development methodologies, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing project governance and management, but it is not the most immediate unsupported assumption in this case.
Question 425
A project team claims all controls were delivered while a critical audit issue remains open in a separate tracker. Which response should an IS auditor recommend as MOST appropriate?
- Reconcile completion deliverables, unresolved risks and assigned follow-up owners before project closure.
- Implement role separation and approved promotion steps for production configuration and releases.
- Escalate unresolved material defects and require qualified, documented acceptance or remediation before go-live.
- Evaluate technical, legal, operational and schedule feasibility separately before approval.
Explanation
Correct Answer
A:Post-implementation assurance requires transparent treatment of residual exceptions. The most directly responsive audit action is: Reconcile completion deliverables, unresolved risks and assigned follow-up owners before project closure. Verification should include: Trace original requirements and audit issues to acceptance evidence, owners and dates.
Incorrect Answers
B:Segregation in release management limits unauthorized or unreviewed production changes. The needed step here is to reconcile completion deliverables, unresolved risks and assigned follow-up owners before project closure.
C:Deployment approval should reflect actual residual risk against pre-agreed go-live criteria. The appropriate remedy is to reconcile completion deliverables, unresolved risks and assigned follow-up owners before project closure.
D:Feasibility is multidimensional and a proposal can be impossible even when code can be built. Instead, the response must reconcile completion deliverables, unresolved risks and assigned follow-up owners before project closure.
Question 426
The audit team proposes this response: Reconcile completion deliverables, unresolved risks and assigned follow-up owners before project closure. For the situation—A project team claims all controls were delivered while a critical audit issue remains open in a separate tracker. Which evidence would BEST demonstrate that the response was effective?
- Inspect change records for cost, dependency, security, testing and stakeholder approvals.
- Trace sampled scope decisions to designated business owners, approvals and baseline changes.
- Trace original requirements and audit issues to acceptance evidence, owners and dates.
- Recalculate total cost of ownership using documented volumes, exit costs and support requirements.
Explanation
Correct Answer
C:Post-implementation assurance requires transparent treatment of residual exceptions. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:Controlled project change management protects objectives and assurance scope from unexamined drift. The relevant control is to trace original requirements and audit issues to acceptance evidence, owners and dates.
B:Project governance must connect change decisions to authorized business objectives and responsibilities. The needed step here is to trace original requirements and audit issues to acceptance evidence, owners and dates.
D:Financial feasibility depends on realistic complete costs and measurable benefit timing. The appropriate remedy is to trace original requirements and audit issues to acceptance evidence, owners and dates.
Question 427
At another organization, closure paperwork omits defect ownership and unresolved vendor commitments. Which assurance principle BEST explains the audit implication?
- Effective project governance requires transparent indicators beyond schedule color codes.
- Feasibility is multidimensional and a proposal can be impossible even when code can be built.
- Migration risk requires a feasible recovery path until converted services are accepted.
- Post-implementation assurance requires transparent treatment of residual exceptions.
Explanation
Correct Answer
D:This principle explains the control or assurance implication in the second, independent scenario. Post-implementation assurance requires transparent treatment of residual exceptions. The auditor should relate that principle to the observed evidence.
Incorrect Answers
A:This is a valid consideration in project governance and management; the scenario instead turns on a different, more specific assurance requirement.
B:This is a valid consideration in business case and feasibility analysis; the scenario instead turns on a different, more specific assurance requirement.
C:This is a valid consideration in system migration, infrastructure deployment, and data conversion; the scenario instead turns on a different, more specific assurance requirement.
Question 428
At another organization, closure paperwork omits defect ownership and unresolved vendor commitments. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?
- A lower purchase price does not prove a positive lifecycle business return.
- Closing the project financially does not automatically close its unresolved security issues.
- A technically successful deployment is not evidence that approval controls were followed.
- Short sprints do not automatically provide effective security and compliance controls.
Explanation
Correct Answer
B:Closing the project financially does not automatically close its unresolved security issues. The underlying issue is that post-implementation assurance requires transparent treatment of residual exceptions.
Incorrect Answers
A:That caution could matter when assessing business case and feasibility analysis, but it is not the most immediate unsupported assumption in this case.
C:That caution could matter when assessing implementation configuration and release management, but it is not the most immediate unsupported assumption in this case.
D:That caution could matter when assessing system development methodologies, but it is not the most immediate unsupported assumption in this case.
Question 429
System performance briefly meets acceptance criteria but fails under normal month-end volume after launch. Which response should an IS auditor recommend as MOST appropriate?
- Require contractually defined quality controls and independent business acceptance of delivered software.
- Evaluate that chosen development methodology retains traceable requirements and quality gates.
- Define validated rollback, retention and cutover decision criteria before retiring legacy services.
- Review operational experience and update controls and capacity plans using actual workload evidence.
Explanation
Correct Answer
D:Implementation success should be reassessed using real operating conditions and feedback. The most directly responsive audit action is: Review operational experience and update controls and capacity plans using actual workload evidence. Verification should include: Compare post-go-live incident metrics and peak-load behavior against acceptance thresholds.
Incorrect Answers
A:Using external developers does not transfer accountability for enterprise requirements and assurance. Instead, the response must review operational experience and update controls and capacity plans using actual workload evidence.
B:Agile delivery can support strong controls when assurance activities are integrated into each iteration. The relevant control is to review operational experience and update controls and capacity plans using actual workload evidence.
C:Migration risk requires a feasible recovery path until converted services are accepted. The needed step here is to review operational experience and update controls and capacity plans using actual workload evidence.
Question 430
The audit team proposes this response: Review operational experience and update controls and capacity plans using actual workload evidence. For the situation—System performance briefly meets acceptance criteria but fails under normal month-end volume after launch. Which evidence would BEST demonstrate that the response was effective?
- Verify approved commits, build artifact hashes, automated gate results and deployment authorization.
- Compare post-go-live incident metrics and peak-load behavior against acceptance thresholds.
- Recalculate total cost of ownership using documented volumes, exit costs and support requirements.
- Review timed exercises, data integrity checks and return-to-service evidence.
Explanation
Correct Answer
B:Implementation success should be reassessed using real operating conditions and feedback. The auditor should retain enough source context to reproduce the conclusion.
Incorrect Answers
A:Secure development requires traceability of changes and trusted software artifacts throughout delivery. The appropriate remedy is to compare post-go-live incident metrics and peak-load behavior against acceptance thresholds.
C:Financial feasibility depends on realistic complete costs and measurable benefit timing. Instead, the response must compare post-go-live incident metrics and peak-load behavior against acceptance thresholds.
D:This observation could inform an assessment of system readiness and implementation testing, but it would not directly demonstrate the corrective action in the present case.