Question 620
The project has the following difficulty: A project manager gives all uncertain events a low likelihood without evidence to keep the dashboard green. What underlying management failure best explains it?
Explanation
Correct Answer
Risk exposure is understated by biased assessments instead of supported estimates. That cause fits the described evidence. The relevant governance rule is: Effective risk analysis requires proportionate evidence and openness about uncertainty. The appropriate response would be to reassess probability and impact using available evidence and stakeholder challenge.
Incorrect Answers
Planning effort precedes agreement on the deliverables that the effort is meant to produce. This could explain a different issue concerning products estimated from task hours only, but the reported conditions instead indicate: Risk exposure is understated by biased assessments instead of supported estimates.
Investment forecasts no longer reflect the project's significant risk profile. This could explain a different issue concerning risk exposure changes expected value, but the reported conditions instead indicate: Risk exposure is understated by biased assessments instead of supported estimates.
Planning precision exceeds what is supported by available information. This could explain a different issue concerning board requests detail for all later stages, but the reported conditions instead indicate: Risk exposure is understated by biased assessments instead of supported estimates.