Question 600
A project manager must triage the following issue: A university discovers an available lab that might cut project cost, but the team treats risk management as threat-only and ignores the opportunity. What initial investigation best distinguishes the causes?
Explanation
Correct Answer
Verify actual lab availability and possible schedule or cost benefits. The risk process has excluded potentially beneficial uncertainty. The resulting action would be: Evaluate the positive uncertainty as an opportunity and decide whether to exploit or enhance it.
Incorrect Answers
Inspect the issue register and approval trail for the language request. That investigation addresses request for change added directly to scope; for the stated decision, verify actual lab availability and possible schedule or cost benefits.
Calculate earliest credible finish against the authorized time limit. That investigation addresses forecast time breach treated as actual only; for the stated decision, verify actual lab availability and possible schedule or cost benefits.
Compare forecast cost and risk with the current stage tolerances. That investigation addresses highlight report hides forecast exception; for the stated decision, verify actual lab availability and possible schedule or cost benefits.