Question 610
Which general PRINCE2 control concept is most pertinent to this problem: A marketing manager is assigned ownership of a high-level data migration risk that only a technical platform lead can control?
Explanation
Correct Answer
Risk owners should be able to manage uncertainty and coordinate response actions. This principle matters here because risk ownership was allocated without the authority or access needed to manage it. The response should tackle the stated project-control deficiency.
Incorrect Answers
Project assurance supports board confidence without becoming a substitute for project management. That principle is more directly associated with project assurance reports only to supplier. The present case concerns the weakness that risk ownership was allocated without the authority or access needed to manage it.
Issues include problems or concerns as well as requests and off-specifications. That principle is more directly associated with problem cannot be assigned to product change. The present case concerns the weakness that risk ownership was allocated without the authority or access needed to manage it.
Supplier representation should carry the accountability needed to deliver required specialist resources. That principle is more directly associated with senior supplier cannot commit capability. The present case concerns the weakness that risk ownership was allocated without the authority or access needed to manage it.