Question 430
Which general PRINCE2 control concept is most pertinent to this problem: An offshore installation is scheduled before a regulator's permit approval, although the team cannot legally begin without the permit?
Explanation
Correct Answer
Useful plans expose product and external dependencies, not just tasks. This principle matters here because the sequence assumes external authorization without reflecting it in delivery logic. The response should tackle the stated project-control deficiency.
Incorrect Answers
Risk budgets should support agreed responses and remain governed by financial tolerances. That principle is more directly associated with risk budget spent without approval. The present case concerns the weakness that the sequence assumes external authorization without reflecting it in delivery logic.
A benefit may depend on organizational changes and other outputs, not only this project. That principle is more directly associated with benefits dependent on another programme. The present case concerns the weakness that the sequence assumes external authorization without reflecting it in delivery logic.
Issues include problems or concerns as well as requests and off-specifications. That principle is more directly associated with problem cannot be assigned to product change. The present case concerns the weakness that the sequence assumes external authorization without reflecting it in delivery logic.