Question 410
A team reflects on this failure: A library digitization project estimates staff hours before anyone has agreed which catalog records and search functions users must receive. What is the most relevant underlying problem?
Explanation
Correct Answer
Planning effort precedes agreement on the deliverables that the effort is meant to produce. That cause fits the described evidence. The relevant governance rule is: Product-based planning identifies required outputs before sequencing activities and estimating work. The appropriate response would be to define the products and descriptions first, then build an activity and resource plan from the resulting product flow.
Incorrect Answers
A subjective acceptance statement cannot reliably determine fitness for purpose. This could explain a different issue concerning acceptance criteria not measurable, but the reported conditions instead indicate: Planning effort precedes agreement on the deliverables that the effort is meant to produce.
Effort expenditure is being mistaken for verified output progress. This could explain a different issue concerning product progress measured only by hours, but the reported conditions instead indicate: Planning effort precedes agreement on the deliverables that the effort is meant to produce.
A future operational accountability gap is hidden from governance planning. This could explain a different issue concerning stakeholder groups omitted from responsibilities, but the reported conditions instead indicate: Planning effort precedes agreement on the deliverables that the effort is meant to produce.