Question 390
An assurance reviewer begins examining: A time-pressed project assigns its project manager to independently assure the same project manager's own stage controls. Which evidence should they inspect first?
Explanation
Correct Answer
Identify who is both controlling and assuring the same work. Self-assessment without independence weakens credible board assurance. The resulting action would be: Separate the assurance assessment from the person being assessed, proportionately to risk.
Incorrect Answers
Check whether the typo affects baselined acceptance or any tolerance. That investigation addresses minor issue overwhelms board reporting; for the stated decision, examine identify who is both controlling and assuring the same work.
Compare the tester's actual calendar with both stage resource forecasts. That investigation addresses resources shared across stages unnoticed; for the stated decision, examine identify who is both controlling and assuring the same work.
Inspect the issue register and approval trail for the language request. That investigation addresses request for change added directly to scope; for the stated decision, examine identify who is both controlling and assuring the same work.