Question 380
Which diagnosis best fits the project scenario: A project introduces new data stewardship roles but omits the department that will operate them from all responsibility maps?
Explanation
Correct Answer
A future operational accountability gap is hidden from governance planning. That cause fits the described evidence. The relevant governance rule is: Organizing includes relationships with business-as-usual roles that will receive products. The appropriate response would be to update the project management team structure and role descriptions to include operational handover ownership.
Incorrect Answers
Progress communication is incomplete for the decisions the board must make. This could explain a different issue concerning risk tolerance data missing from highlight, but the reported conditions instead indicate: A future operational accountability gap is hidden from governance planning.
A foreseeable negative outcome has been omitted from investment justification. This could explain a different issue concerning disbenefit hidden in service redesign, but the reported conditions instead indicate: A future operational accountability gap is hidden from governance planning.
Planning effort precedes agreement on the deliverables that the effort is meant to produce. This could explain a different issue concerning products estimated from task hours only, but the reported conditions instead indicate: A future operational accountability gap is hidden from governance planning.