Question 440
The project has the following difficulty: A stage is two days late but remains well inside its time tolerance; staff immediately replace the stage plan with an exception plan. What underlying management failure best explains it?
Explanation
Correct Answer
A normal in-tolerance adjustment has been mistaken for an exception condition. That cause fits the described evidence. The relevant governance rule is: An exception plan replaces an approved plan only when authorized in response to a forecast exception. The appropriate response would be to manage the variance within delegated stage controls rather than replacing the plan without a forecast tolerance breach.
Incorrect Answers
An issue's urgency is being mistaken for a tolerance exception. This could explain a different issue concerning urgent issue confused with exception, but the reported conditions instead indicate: A normal in-tolerance adjustment has been mistaken for an exception condition.
A replacement baseline has been used without authorized exception direction. This could explain a different issue concerning exception plan not authorized before use, but the reported conditions instead indicate: A normal in-tolerance adjustment has been mistaken for an exception condition.
Local change approval has been granted without protecting the board's tolerance authority. This could explain a different issue concerning change authority with no limits, but the reported conditions instead indicate: A normal in-tolerance adjustment has been mistaken for an exception condition.