Question 230
A project planned to spend $100,000 by month-end but has completed only $80,000 of budgeted work and spent $90,000. What is cost variance (EV − AC)?
Explanation
Correct Answer
Earned value is $80,000 and actual cost is $90,000; cost variance = $80,000 − $90,000 = −$10,000.
Incorrect Answers
A negative $20,000 compares earned value to planned value, which is schedule variance.
A positive $20,000 reverses the schedule-variance direction and ignores actual cost.
A positive $10,000 reverses the sign of the overrun.