Question 130
The team follows this response: Rebaseline only after authorized substantive changes, retaining variance history. Context: approved schedule changes create conflict between current dates and approved baseline. Which evidence BEST verifies the intended outcome?
Explanation
Correct Answer
Compare approved baseline versions and decision records against the forecast. That evidence tests the response to approved schedule changes create conflict between current dates and approved baseline instead of an unrelated project condition.
Incorrect Answers
This check would validate resource leveling, not the result required by the baseline revision case. Resource leveling may change activity dates to match capacity.
This check would validate finish-to-start dependency, not the result required by the baseline revision case. Finish-to-start enforces ordered completion before dependent work starts.
This check would validate critical path impact, not the result required by the baseline revision case. Critical path activities govern the earliest possible completion date.