Question 120
An application deployment must follow final security approval. Which caution is MOST directly relevant to the project manager's decision?
Explanation
Correct Answer
A visual order on a Gantt chart is not proof the dependency is enforced. The underlying reason is that finish-to-start enforces ordered completion before dependent work starts.
Incorrect Answers
This is a caution about critical path impact, not the immediate risk in finish-to-start dependency. Critical path activities govern the earliest possible completion date.
This is a caution about agile estimation, not the immediate risk in finish-to-start dependency. Story points express relative effort and uncertainty within a team.
This is a caution about baseline revision, not the immediate risk in finish-to-start dependency. Baseline control distinguishes approved commitments from current forecasts.






CompTIA Project+ (PK0-005) Practice Tests