Question 570
An assurance reviewer begins examining: An organization quality team audits the project management system while product tests are ongoing, and the project manager claims its audit replaces product quality control. Which evidence should they inspect first?
Explanation
Correct Answer
Compare audit findings with required product test results. Assurance of process compliance is being confused with verification of product quality. The resulting action would be: Continue product-specific quality control while acknowledging the separate assurance review.
Incorrect Answers
Ask who independently verifies real user fitness for purpose. That investigation addresses independent user assurance absent; for the stated decision, compare audit findings with required product test results.
Calculate the impact of the issue on current stage and project tolerances. That investigation addresses urgent issue confused with exception; for the stated decision, compare audit findings with required product test results.
Compare the proposed objective change with the team manager's formal mandate. That investigation addresses team manager signs board strategy; for the stated decision, compare audit findings with required product test results.