Question 550
For the project situation—A test uncovers a serious defect, the developer marks it fixed, and the project manager closes the quality event without rerunning verification—which underlying method concept should guide the decision?
Explanation
Correct Answer
A quality finding should be resolved with demonstrated conformity rather than assertion. This principle matters here because a claimed fix has replaced objective proof of restored product quality. The response should tackle the stated project-control deficiency.
Incorrect Answers
Issue management requires tracking decisions through effective resolution. That principle is more directly associated with issue register has no closure evidence. The present case concerns the weakness that a claimed fix has replaced objective proof of restored product quality.
Product flow diagrams describe dependencies among planned outputs. That principle is more directly associated with product flow starts with testing before build. The present case concerns the weakness that a claimed fix has replaced objective proof of restored product quality.
Daily logs assist informal control but do not substitute for formal governance where required. That principle is more directly associated with daily log includes unowned major decision. The present case concerns the weakness that a claimed fix has replaced objective proof of restored product quality.