Question 490
Which PRINCE2 management principle or mechanism best explains the appropriate response to: A six-week internal form redesign is divided into ten formal management stages with separate authorization meetings?
Explanation
Correct Answer
Management stages can be tailored to project complexity and decision needs. This principle matters here because stage boundaries were inserted without proportional risk or investment justification. The response should tackle the stated project-control deficiency.
Incorrect Answers
Project risk management includes threats arising beyond direct delivery control. That principle is more directly associated with cross-project dependency threat. The present case concerns the weakness that stage boundaries were inserted without proportional risk or investment justification.
A project brief supports the starting-up decision before detailed initiation products exist. That principle is more directly associated with unclear project brief at authorization. The present case concerns the weakness that stage boundaries were inserted without proportional risk or investment justification.
Justification involves realistic evaluation of both benefits and disbenefits. That principle is more directly associated with disbenefit hidden in service redesign. The present case concerns the weakness that stage boundaries were inserted without proportional risk or investment justification.