Question 470
An assurance reviewer investigates: A planning exercise includes launch milestones but no owner or capacity for the benefits review six months after closure. Which root cause is most consistent with the evidence?
Explanation
Correct Answer
Planning stops at output delivery even though planned outcomes need operational follow-through. That cause fits the described evidence. The relevant governance rule is: Project planning supports transition and realization of intended outcomes after delivery. The appropriate response would be to link post-project benefit measurement responsibility and timing to the project plan and management approaches.
Incorrect Answers
The benefits forecast ignores dependencies beyond this project's direct delivery. This could explain a different issue concerning benefits dependent on another programme, but the reported conditions instead indicate: Planning stops at output delivery even though planned outcomes need operational follow-through.
Expected benefits occur after formal project closure and would otherwise go unverified. This could explain a different issue concerning benefits management timing after closure, but the reported conditions instead indicate: Planning stops at output delivery even though planned outcomes need operational follow-through.
Post-project benefit measurement has been neglected after delivery completion. This could explain a different issue concerning benefits review planned but never reported, but the reported conditions instead indicate: Planning stops at output delivery even though planned outcomes need operational follow-through.