Question 260
The project has the following difficulty: Two related improvement projects both include the same annual help-desk saving in their business cases, inflating portfolio-level value. What underlying management failure best explains it?
Explanation
Correct Answer
The same financial outcome is attributed to multiple independent investments. That cause fits the described evidence. The relevant governance rule is: Business justification requires credible attribution of costs and benefits. The appropriate response would be to reconcile benefits with the portfolio or programme owner and remove double counting from both cases.
Incorrect Answers
Component specifications are not integrated into a clear project-level product definition. This could explain a different issue concerning project product description missing, but the reported conditions instead indicate: The same financial outcome is attributed to multiple independent investments.
The board lacks balanced information to decide on further investment. This could explain a different issue concerning stage end report missing business status, but the reported conditions instead indicate: The same financial outcome is attributed to multiple independent investments.
Risk ownership was allocated without the authority or access needed to manage it. This could explain a different issue concerning risk owner cannot influence response, but the reported conditions instead indicate: The same financial outcome is attributed to multiple independent investments.