Question 250
Which general PRINCE2 control concept is most pertinent to this problem: The project board is asked to authorize initiation of a public records modernization effort before the outline business case explains why the change is needed?
Explanation
Correct Answer
A project brief supports the starting-up decision before detailed initiation products exist. This principle matters here because the board lacks enough preliminary justification to authorize further investment. The response should tackle the stated project-control deficiency.
Incorrect Answers
Stage boundary reporting informs whether continued investment is warranted. That principle is more directly associated with stage end report missing business status. The present case concerns the weakness that the board lacks enough preliminary justification to authorize further investment.
The executive leads business justification while the project manager manages authorized work. That principle is more directly associated with executive delegates investment decision downwards. The present case concerns the weakness that the board lacks enough preliminary justification to authorize further investment.
Management stages can be tailored to project complexity and decision needs. That principle is more directly associated with too many management stages for simple project. The present case concerns the weakness that the board lacks enough preliminary justification to authorize further investment.