Question 400
The implementer is warned about this situation: A retailer promises to address six urgent risks but sets no owners or acceptance checkpoints. Which mistaken assumption would most directly undermine an effective response?
Explanation
Correct Answer
Treating a risk register entry as an actionable deployment plan without owners or dates. This is the most directly harmful practice for the specific issue where a retailer promises to address six urgent risks but sets no owners or acceptance checkpoints. It could leave the organization facing unfulfilled treatment commitments and uncontrolled late delivery. Instead, the implementer should plan control implementation with accountable ownership, resources, timing and verification. A suitable check is that progress records show completion and tested effectiveness against the treatment plan.
Incorrect Answers
Freezing ISMS planning assumptions at an old organizational structure. This would be a concern in a different topic, such as when a retailer expands into another jurisdiction but its security plan ignores new contractual and statutory constraints. It is not the defining mistaken approach for the problem described. The error to avoid in this case is treating a risk register entry as an actionable deployment plan without owners or dates. The linked exposure is unfulfilled treatment commitments and uncontrolled late delivery. Case: A retailer promises to address six urgent risks but sets no owners or acceptance checkpoints.
Treating the existence of a document title as proof that an associated requirement is implemented. This would be a concern in a different topic, such as when an insurance firm has scattered controls and cannot identify which governance and process gaps precede certification. It is not the defining mistaken approach for the problem described. The error to avoid in this case is treating a risk register entry as an actionable deployment plan without owners or dates. The linked exposure is unfulfilled treatment commitments and uncontrolled late delivery. Case: A retailer promises to address six urgent risks but sets no owners or acceptance checkpoints.
Assuming every risk must be reduced through a new technology control. This would be a concern in a different topic, such as when a government contractor must decide whether to eliminate, modify, share or retain a sensitive data-processing risk. It is not the defining mistaken approach for the problem described. The error to avoid in this case is treating a risk register entry as an actionable deployment plan without owners or dates. The linked exposure is unfulfilled treatment commitments and uncontrolled late delivery. Case: A retailer promises to address six urgent risks but sets no owners or acceptance checkpoints.