Question 290
In the following case: An ISP has a list of scored risks but no decision rule to identify which require treatment. Which approach should the ISMS lead most specifically avoid?
Explanation
Correct Answer
Prioritizing the easiest purchase rather than the risks exceeding acceptance limits. This is the most directly harmful practice for the specific issue where an ISP has a list of scored risks but no decision rule to identify which require treatment. It could leave the organization facing high-exposure risks remaining untreated while less consequential work consumes resources. Instead, the implementer should compare analyzed risk levels to approved evaluation and acceptance criteria. A suitable check is that treatment prioritization follows approved criteria and departures are justified and authorized.
Incorrect Answers
Assuming a control installer may silently accept every remaining business consequence. This would be a concern in a different topic, such as when a platform operator signs an exception accepting a compliance exposure without business authorization. It is not the defining mistaken approach for the problem described. The error to avoid in this case is prioritizing the easiest purchase rather than the risks exceeding acceptance limits. The linked exposure is high-exposure risks remaining untreated while less consequential work consumes resources. Case: An ISP has a list of scored risks but no decision rule to identify which require treatment.
Assuming only executive leadership counts as an interested party for ISMS planning. This would be a concern in a different topic, such as when a fintech builds safeguards for internal operations but overlooks payment-partner notification obligations. It is not the defining mistaken approach for the problem described. The error to avoid in this case is prioritizing the easiest purchase rather than the risks exceeding acceptance limits. The linked exposure is high-exposure risks remaining untreated while less consequential work consumes resources. Case: An ISP has a list of scored risks but no decision rule to identify which require treatment.
Choosing a rating method solely to produce low scores for a favored project. This would be a concern in a different topic, such as when a bank treats every identified threat as unacceptable because impact criteria were never defined. It is not the defining mistaken approach for the problem described. The error to avoid in this case is prioritizing the easiest purchase rather than the risks exceeding acceptance limits. The linked exposure is high-exposure risks remaining untreated while less consequential work consumes resources. Case: An ISP has a list of scored risks but no decision rule to identify which require treatment.